City earmarks $138.6M for rapid transit

The City of Winnipeg plans to set aside $138.6 million over the next three years to extend the Southwest Transitway to the University of Manitoba.

The city has earmarked $1.1 million in the 2013 capital budget to complete the design of the second leg of the Southwest Transitway, which has a projected cost of $350 million, as well as begin the design of an East Transitway that would connect downtown to Transcona.

A further $10 million has been earmarked for the Southwest Transitway in the 2014 capital budget, with another 127.5 million dedicated to the 2015 capital budget.

"The whole purpose of today quite simply is to show the commitment of city council," Mayor Sam Katz said this morning at the Winnipeg Transit's Fort Rouge garage.

The city and province do not have a deal with the province or Ottawa to complete the Southwest Transitway.

The announcement effectively places the funding onus on the Selinger government, which has said it will pay for the corridor but has not come to any agreement with the city.

Katz said he hopes Broadway will commit $137.5 million toward the second leg of the Southwest Transit way and also match the city's $1.1-million design commitment.

Ottawa has been asked to spend $75 million on the Southwest Transitway, using a fund devoted to public-private partnerships, Katz said.

The second leg will be operated by the city but could be constructed as a design-build public-private partnership, the mayor said.

Province willing to pay $117M

Manitoba Local Government Minister Ron Lemieux said he is thrilled to see the city commit to completing the transitway, and said the province remains committed to paying for one-third of the tab.

That works out $117 million, or $20.5 million shy of what the city wants to see from the province. But Lemieux said discussions with Ottawa may yield more federal dollars.

The first phase of the Southwest Transitway, which runs from Queen Elizabeth Way to Jubilee Avenue, opened in April.

If all funding is in place, construction on the second phase could begin in 2015 and be completed in 2018, said Winnipeg Transit director Dave Wardrop.

The second leg will most likely follow a dogleg route through Fort Garry instead of parallel to Pembina Highway. This route would run west through the Parker neighbourhood and then south along a Manitoba Hydro corridor.

Winnipeg Transit is expected to recommend this alignment to city council in early 2013.

History

Updated on Thursday, December 13, 2012 at 11:29 AM CST: Updates from news conference.

4:41 PM: Adds comment from province.

Fact Check

Fact Check

Have you found an error, or know of something we’ve missed in one of our stories? Please use the form below and let us know.

* Required
  • Please post the headline of the story or the title of the video with the error.

  • Please post exactly what was wrong with the story.

  • Please indicate your source for the correct information.

  • Please include any contact information you may have.

  • Yes

    No

  • This will only be used to contact you if we have a question about your submission, it will not be used to identify you or be published.

  • This will only be used to contact you if we have a question about your submission, it will not be used to identify you or be published.

  • Are you blue? If you can see this, leave it blank and get some CSS support.

You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is register and/or login and you can join the conversation and give your feedback.

Have Your Say

New to commenting? Check out our Frequently Asked Questions.

The Winnipeg Free Press does not necessarily endorse any of the views posted. By submitting your comment, you agree to our Terms and Conditions. These terms were revised effective April 16, 2010.

letters

Make text: Larger | Smaller

LATEST VIDEO

Homicide unit investigating Roblin Boulevard incident

View more like this

Photo Store Gallery

  • A group of Horese pose for the camera in the early evening light at Southcreek Stables in Stl Norbert Wednessday. Sept  14, 2011 (RUTH BONNEVILLE) / WINNIPEG FREE PRESS)
  • A monarch butterfly looks for nectar in Mexican sunflowers at Winnipeg's Assiniboine Park Monday afternoon-Monarch butterflys start their annual migration usually in late August with the first sign of frost- Standup photo– August 22, 2011   (JOE BRYKSA / WINNIPEG FREE PRESS)

View More Gallery Photos

Poll

Should Victoria Day be renamed to honour aboriginals?

View Results

View Related Story

Ads by Google