Power flowing from massive hydro project

  • Print

Power is now flowing from a massive Manitoba Hydro project, as the Wuskwatim Generating Station officially comes to life.

On Thursday morning, Premier Greg Selinger and other officials flew to northern Manitoba to mark the launch of operations at the Burntwood River site. The $1.37-billion project has been six years in the making, and will send 200 megawatts of energy into the Manitoba grid.

The first of Wuskwatim’s three huge turbines started turning on June 22.

The dam was developed by the Wuskwatim Power Ltd. Partnership, which is a joint venture between the Nisichawayasihk Cree Nation and Manitoba Hydro.

The station was built on traditional Cree land about 45 kilometres southwest of Thompson, and the community has the option of claiming up to 33 per cent ownership of the project.

The First Nation must decide by July 2013 how much it will claim, though Chief Jerry Primrose has already confirmed it will take a "significant" ownership position. Manitoba Hydro is also working with Nisichawayasihk to train and hire local workers.

"This is an exciting time for our community," Primrose said on Thursday. "For the first time, our people will benefit in a more meaningful way from hydro development, rather than just through compensation after the fact."

Fact Check

Fact Check

Have you found an error, or know of something we’ve missed in one of our stories?
Please use the form below and let us know.

* Required
  • Please post the headline of the story or the title of the video with the error.

  • Please post exactly what was wrong with the story.

  • Please indicate your source for the correct information.

  • Yes

    No

  • This will only be used to contact you if we have a question about your submission, it will not be used to identify you or be published.

  • Cancel

Having problems with the form?

Contact Us Directly
  • Print

You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is be a Winnipeg Free Press print or e-edition subscriber to join the conversation and give your feedback.

You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is be a Winnipeg Free Press print or e-edition subscriber to join the conversation and give your feedback.

Have Your Say

New to commenting? Check out our Frequently Asked Questions.

Have Your Say

Comments are open to Winnipeg Free Press print or e-edition subscribers only. why?

Have Your Say

Comments are open to Winnipeg Free Press Subscribers only. why?

The Winnipeg Free Press does not necessarily endorse any of the views posted. By submitting your comment, you agree to our Terms and Conditions. These terms were revised effective April 16, 2010.

letters

Make text: Larger | Smaller

LATEST VIDEO

Chief justices breakdown cameras in courtroom project

View more like this

Photo Store Gallery

  • Hay bales sit under a rainbow just west of Winnipeg Saturday, September 3, 2011.(John Woods/Winnipeg Free Press)
  • Challenges of Life- Goose Goslings jump over railway tracks to catch up to their parents at the Canadian Pacific Railway terminalon Keewatin St in Winnipeg Thursday morning. The young goslings seem to normally hatch in the truck yard a few weeks before others in town- Standup photo- ( Day 4 of Bryksa’s 30 day goose project) - Apr 30, 2012   (JOE BRYKSA / WINNIPEG FREE PRESS)

View More Gallery Photos

Poll

Do you agree with the province’s crackdown on flavoured tobacco products?

View Results

View Related Story

Ads by Google