A bad case of heads buried in the sand

Audit needed into police headquarters fiasco

In the original version of the British sitcom Yes, Minister, the cynical Sir Humphrey Appleby offered up advice about the consequences of investigations.

"Never set up an inquiry unless you know in advance what its findings will be," advised Appleby, providing a road map for decisions taken by real-life elected officials.

Audits and inquiries can inflict a tremendous amount of political damage. The review of Winnipeg's fire-paramedic station replacement program, for example, was a disaster for Mayor Sam Katz, as it concluded his friend, Phil Sheegl, Winnipeg's former CAO, oversaw an over-budget and badly managed construction project plagued by unfair contract awards.

The pilloried fire-paramedic station project cost taxpayers $3.3 million more than its original budget. The new police headquarters is far more problematic, as it now stands at $76 million above its original target.

Like the fire-paramedic program, the new cop shop has also been plagued by amendments to the construction model and several sole-sourced contracts. City council, however, chose to follow Appleby's advice on Wednesday rather than get to the bottom of the police HQ conundrum.

In an astounding decision, council voted 9-7 to kill a motion to conduct an audit of the project. All seven members of executive policy committee -- plus Couns. Devi Sharma (Old Kildonan) and Thomas Steen (Elmwood) -- voted against any further investigation in what appeared to be a whipped vote.

It's disappointing to see nine members of council insert their noggins in the sand. It's also amazing, as several know there are serious problems with the police HQ.

Transcona Coun. Russ Wyatt, for example, said it's obvious "absolute incompetence" at the highest level of the civic administration plagued the police HQ. But in the next breath, Wyatt said an audit would be a waste of money because it would only come to the same conclusion as the fire-paramedic station audit: The individual leading the project was "way over his head," in Wyatt's words.

Without mentioning Sheegl's name, Wyatt repeated the last batch of police-HQ cost overruns -- $17.2 million in design changes not covered by a toothless "guaranteed maximum price" agreement -- ultimately cost the former CAO his job.

Wyatt's ostrich imitation led several councillors to point out only an audit can determine precisely what went wrong. "Whether we realize it or not, we've lost the public trust," said St. Boniface Coun. Dan Vandal.

Katz's uncomfortable coalition would have none of it. St. Norbert Coun. Justin Swandel, who dismissed the fire-paramedic station audit as flawed, claimed council was kept abreast of every change to the police HQ project.

That simply isn't true. A 2011 report about $28 million in cost overruns didn't mention a proposed "guaranteed maximum price" agreement would be based on a design that was only 30 per cent complete.

Nonetheless, Swandel derided his colleagues for not reading reports. "If you want an audit, maybe we should audit IQ around this chamber," he said.

But the deputy mayor wasn't done. He then accused the media of selectively reporting facts and claimed all answers to questions about the project could be obtained "in five minutes."

In reality, the city kept basic information about the police HQ hidden from the public for more than three years. The initial 2010 city request for proposals for a consultant to design the police HQ was only published Friday, after the Free Press asked why this set of documents was not posted on the city's website.

These documents, by the way, show the city amended the police HQ construction job to a design-build model on June 8, 2010, near the beginning of the procurement phase for the project. In other words, the city made a deliberate, early decision to ask for a design that was "30 per cent complete" as part of a plan to finish the design on the fly.

This is very, very important. A new report to council -- held up by Katz and Swandel as the definitive account of the police-HQ saga -- claims the construction model was amended because of design problems discovered partway through the project.

This is an obfuscation, if not an outright lie. The construction model was amended in June 2010 and the first design contract wasn't awarded until August 2010. Design problems were not reported until 2011 -- and may have resulted, ironically, from the early decision to reduce the scope of the initial design work as part of changes to the construction model.

"Read the report, the answers are there," Katz implored as part of his argument against an audit. No, they are not, Mr. Mayor. Do the right thing and request an audit.

bartley.kives@freepress.mb.ca

Republished from the Winnipeg Free Press print edition November 21, 2013 A5

You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is be a Winnipeg Free Press print or e-edition subscriber to join the conversation and give your feedback.

Have Your Say

New to commenting? Check out our Frequently Asked Questions.

Have Your Say

Comments are open to Winnipeg Free Press print or e-edition subscribers only. why?

Have Your Say

Comments are open to Winnipeg Free Press Subscribers only. why?

The Winnipeg Free Press does not necessarily endorse any of the views posted. By submitting your comment, you agree to our Terms and Conditions. These terms were revised effective January 2015.

Scroll down to load more

Top