City on hook for road-work cost overruns?
Waverley West price escalating, mayor told
The construction of new major roads through Waverley West is as much as $20 million over budget -- and the City of Winnipeg may be stuck with the tab.
Mayor Sam Katz and several city councillors have been warned the Waverley West Arterial Roads Project, which includes the extension of Kenaston Boulevard from Bishop Grandin Boulevard to the Perimeter Highway, has ballooned by tens of millions over its original $54.7-million budget.
All three levels of government agreed in 2009 to shoulder an equal share of the cost of the project, which also includes changes to Waverley Street as well as new intersections.
The money was placed in the city's capital budget in 2010 but work did not begin in earnest until the past two summers. One of the delays was the result of an environmental assessment ordered up by Ottawa to ensure the project did not impact fish habitat, said St. Norbert Coun. Justin Swandel.
Changes to Kenaston Boulevard created a new crossing of a body of water called the Lot 16 Drain, which runs alongside Bishop Grandin Boulevard on its way to the Red River.
"With any big federal project, they have the right to say they want an environmental assessment," said Swandel, who surmised the study pushed back the start date of the Kenaston work by at least 18 months.
A change to the intersection at the Perimeter Highway may be the province's responsibility, Swandel added.
Katz said he is still waiting to hear an explanation for the cost overruns, but said initial information suggests the hike is not entirely the city's fault. The 2013 capital budget may have to address the funding shortfall, the mayor said.
Katz said he fears the city may wind up eating the cost increase on its own, regardless of who's to blame. Infrastructure-funding deals involving three levels of government typically don't include contingencies for cost overruns, he said.
"It's never one-third, one-third, one-third. The city always ends up paying more money," said Katz, adding preliminary design work that could reduce the potential for cost overruns also never winds up getting covered by tri-level funding deals. "The city is always left holding the bag."
Katz said he would prefer to see Building Canada Fund-style pots of money replaced with a new infrastructure-funding formula for cities. Katz has been arguing for a share of growth revenues since early 2005.
Swandel, meanwhile, would like to shelve a new planning framework for Waverley West that includes old road locations without taking other changes to the area into account. For example, Pembina Trails School Division now plans to build four schools in Waverley West instead of the six new institutions envisioned when the city, province, school division and developer Ladco drew up plans for a more pedestrian-friendly new suburb.
On Tuesday, Swandel attempted to convince council's property committee to hold off on approving a new Waverley West planning framework. But he was ruled out of order by committee chairman Jeff Browaty (North Kildonan) because public hearings about the plan had closed.
"I was trying to speak in generalities about roads and schools because there are big changes out there," said Swandel, who attempted to limit further Waverley West development until a new school was built.
"This is not me trying to pull a fast one on somebody. These are very serious issues."
Republished from the Winnipeg Free Press print edition November 8, 2012 A8
More Local
- Back to Top
- Return to Local
More Local
(1 of 20 articles for today)
Jockey club launches $350-M civil suit against province
1:00 AM 0THE Manitoba Jockey Club is continuing its fight for survival, launching civil actions against the Selinger government, Finance Minister Stan ...
Poll
Most Popular Local
- Flood money paid for CEO's romantic trip
- Crash claims two young women, RCMP say
- First Nation celebrates groundbreaking on city's first urban reserve
- Housing a little more expensive in Manitoba: RBC
- Lake St. Martin reserve close to getting new home
- Some good news, some bad news from weatherman
- 'I told them, "I think that guy downstairs is dead"': teen witness at murder trial
- Jockey club launches $350-M civil suit against province
- Drug dealer sentenced to 3½ years in prison
- Manitoba senators weigh in on scandal
- Charleswood deaths being investigated as domestic incident
- Man charged, victims identified in double homicide
- Man dies after being pulled from vehicle submerged in Winnipeg retention pond
- Flood money paid for CEO's romantic trip
- Crash claims two young women, RCMP say
- Developers to unveil plans for bold downtown tower
- Police identify slaying victims
- Apple trick on Ellen falls short for city woman
- Aboriginal leader Elijah Harper dies
- 'Responsible Winnipeg' ads appear on sign run by mayor-owned Goldeyes' baseball park
- Hundreds pitch in to dig out houses damaged, destroyed by Ochre Beach ice floe
- A child-custody catastrophe
- Charleswood deaths being investigated as domestic incident
- Man charged, victims identified in double homicide
- Co-worker 'sick' today? Maybe it's the $17M flu
- Man dies after being pulled from vehicle submerged in Winnipeg retention pond
- '2 minutes after I read the winning numbers, I retired': Winnipeg lotto winner
- Parents, community relieved and elated as missing boy found safe
- No threat from bag found at Winnipeg Square
- Man missing since 2009 found safe
- Baby steps toward empathy
- U of M president targets low tuition
- Flood money paid for CEO's romantic trip
- City chiropractor guilty of beating, sexually assaulting ex-girlfriend
- Drug dealer sentenced to 3½ years in prison
- New units to help keep invasive aquatic species out of province
- Housing a little more expensive in Manitoba: RBC
- Jockey club launches $350-M civil suit against province
- New provincial restrictions on buying cigarettes
- Bethania board puts CEO on leave amid probe
- Developers to unveil plans for bold downtown tower
- Crushing blow for amateur sport
- Aboriginal leader Elijah Harper dies
- Fishing for fashion
- Famous city grocer loved job, customers
- Core grocer a challenge: expert
- Grocer Joe Cantor dies at 88
- Newly minted MD a beacon for kids in youth program
- North End proud
- Power restored to Linden Woods after goose collides with lines
- Hundreds pitch in to dig out houses damaged, destroyed by Ochre Beach ice floe
- Mental-health patients get own ER
- A child-custody catastrophe
- An uncommon phenomenon
- Steen invests $1M in family entertainment centre
- Earls on Main going, but new one coming
- Province introduces changes to rules governing landlords, renters
- Developers to unveil plans for bold downtown tower
- Crushing blow for amateur sport
- Boost same-sex curricula: union
Ads by Google











You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is register and/or login and you can join the conversation and give your feedback.
Have Your Say
New to commenting? Check out our Frequently Asked Questions.
The Winnipeg Free Press does not necessarily endorse any of the views posted. By submitting your comment, you agree to our Terms and Conditions. These terms were revised effective April 16, 2010.