Construction company sues over stadium delay

Alleges Quebec firm at fault for extra season at Canad Inns

  • Print

2Stuart Olson Dominion Construction filed a statement of claim in Manitoba Court of Queen's Bench against Quebec-based Structal Heavy Steel for special and general damages, which currently is at more than $14.3 million.

Dominion is also suing Structal for $1 million in punitive damages for what it alleges were the steel company's "capricious, high-handed, malicious, oppressive and arbitrary manner for the purposes of its own interest."

Dominion, which has its head office in Calgary and has construction-management offices in Winnipeg, is claiming because of construction delays, allegedly caused by Structal, Investors Group Field did not open in time for the Blue Bombers this past season, forcing the team to spend one more season at Canad Inns Stadium.

The lawsuit also alleges the delays led to other extra costs, including fixing water-damaged portions of the facility that had already been constructed and having to store stadium seating until they could be installed.

Evan Johnson, vice-president and general counsel of the Churchill Corporation, the parent company of Stuart Olson Dominion, would only verify "we have sued Structal and it relates to the Winnipeg stadium job."

As to the punitive damages sought, Johnson said "punitive is in the statement of claim.

"We wouldn't have put it there if we had not thought that through."

A spokesman for Structal said the company does not comment on issues before the courts.

In the court documents, Dominion said it entered into a contract with BBB Stadium Inc. to be the construction manager of the stadium construction on Dec. 17, 2010.

Dominion said on Feb. 2, 2011, after a tending and bidding process, it agreed to pay Structal more than $44 million to supply and install structural steel, a roof bow-truss scheme, precast bleachers and vomitory walls to allow people to enter and leave the stadium seating area.

Dominion alleges it told Structal the clock was ticking and the construction had to begin on Dec. 3, 2010, and be substantially finished by June 1, 2012.

Dominion alleges not only were these dates not met, but Structal also cost Dominion extra money because of the delays, including water damage to east suites due to the roof not being finished, and temporary winter heating.

The allegations have not been proven in court and no statement of defence has been filed.

kevin.rollason@freepress.mb.ca

Republished from the Winnipeg Free Press print edition January 29, 2013 B3

Fact Check

Fact Check

Have you found an error, or know of something we’ve missed in one of our stories?
Please use the form below and let us know.

* Required
  • Please post the headline of the story or the title of the video with the error.

  • Please post exactly what was wrong with the story.

  • Please indicate your source for the correct information.

  • Yes

    No

  • This will only be used to contact you if we have a question about your submission, it will not be used to identify you or be published.

  • Cancel

Having problems with the form?

Contact Us Directly
  • Print

You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is be a Winnipeg Free Press print or e-edition subscriber to join the conversation and give your feedback.

You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is be a Winnipeg Free Press print or e-edition subscriber to join the conversation and give your feedback.

Have Your Say

New to commenting? Check out our Frequently Asked Questions.

Have Your Say

Comments are open to Winnipeg Free Press print or e-edition subscribers only. why?

Have Your Say

Comments are open to Winnipeg Free Press Subscribers only. why?

The Winnipeg Free Press does not necessarily endorse any of the views posted. By submitting your comment, you agree to our Terms and Conditions. These terms were revised effective April 16, 2010.

letters

Make text: Larger | Smaller

LATEST VIDEO

Key of Bart - Take It Easy

View more like this

Photo Store Gallery

  • A young goose gobbles up grass at Fort Whyte Alive Monday morning- Young goslings are starting to show the markings of a adult geese-See Bryksa 30 day goose challenge- Day 20– June 11, 2012   (JOE BRYKSA / WINNIPEG FREE PRESS)
  • A baby Red Panda in her area at the Zoo. International Red Panda Day is Saturday September 15th and the Assiniboine Park Zoo will be celebrating in a big way! The Zoo is home to three red pandas - Rufus, Rouge and their cub who was born on June 30 of this year. The female cub has yet to be named and the Assiniboine Park Zoo is asking the community to help. September 14, 2012  BORIS MINKEVICH / WINNIPEG FREE PRESS

View More Gallery Photos

Poll

Do you like Gord Steeves’ idea to sell four city-owned golf courses to fund road renewal?

View Results

View Related Story

Ads by Google