Police HQ contracts added to audit list

Top bureaucrat denies procurement rules violated

  • Print

AUDITORS will review how the city awarded contracts to manage construction of the new police headquarters despite assurances from chief administrative officer Phil Sheegl that officials followed proper procedures.

On Wednesday, Sheegl responded to concerns raised by former mayoral adviser Brian Kelcey, who alleged city officials may have violated procurement rules when they awarded the Dunmore Corporation the contract to manage construction of the new HQ on Graham Avenue. The Dunmore Corporation's president is Ossama AbouZeid, who also oversaw construction of Investors Group Field, the Winnipeg Blue Bombers' new stadium at the University of Manitoba.

In a letter to council, Kelcey said the city's policy is to tender consultant contracts that exceed $100,000, but a recent city financial report suggests Winnipeg's public service sole-sourced a contract to Dunmore and paid the company $262,580 in fees to manage the police headquarters redevelopment.

The letter also raised concern Adjeleian Allan Rubeli, an Ottawa engineering firm hired to help manage the headquarters project, has been paid $4.5 million. The city initially sole-sourced a contract to Adjeleian Allan Rubeli for a fee that was not to exceed $2.6 million, Kelcey's letter states.

Sheegl said the contracts are not governed by the policy that requires Winnipeg to tender consultant contracts more than $100,000 as they are not consulting contracts, but a "direct service" for project management. He said the city sole-sourced a contract to Dunmore Corporation because of its expertise in constructing football stadiums.

At the time Dunmore was hired, Sheegl said designing the headquarters was well underway and the city was working to guarantee a maximum price on construction so it would not spiral out of control.

He said AbouZeid was just completing work on the football stadium and it would've taken weeks to tender a contract and bring someone up to speed.

"I'm the chair of BBB Stadium and watched him hands-on and the great work that he did there and he comes highly recommended," Sheegl said on Wednesday, following council's last meeting of 2012.

BBB Stadium Inc. is a non-profit corporation held equally by the city, the U of M and the Winnipeg Football Club. BBB stands for Blue Bombers and Bisons.

Sheegl also clarified there was no cost overrun on engineering work and said Adjeleian Allan Rubeli completed what it was paid $2.6 million to do. The firm was also paid to complete the work a previous engineering firm did not finish because they parted ways with the city, he said.

Sheegl said the firm was paid with money already in the budget.

Finance chairman Coun. Russ Wyatt (Transcona) said he forwarded Kelcey's letter to the city auditor and confirmed the construction management contracts will be included in the ongoing city real estate audit. Wyatt said the matter will be "a priority."

Sheegl said there's nothing in the letter that needs to be further addressed, but Wyatt is well within his rights to ask auditors to look into issues he believes need to be reviewed.

Kelcey said he's glad the CAO responded to his concerns, but he still thinks officials violated tender policy. He said city administration should have been able to immediately clarify who was hired and who authorized it, and the fact auditors will review the contracts shows his concerns aren't "frivolous."

"It's not rocket science," Kelcey said. "A well-functioning government keeps track of these things to answer questions quickly -- not a day later."

jen.skerritt@freepress.mb.ca

Republished from the Winnipeg Free Press print edition December 13, 2012 B1

Fact Check

Fact Check

Have you found an error, or know of something we’ve missed in one of our stories?
Please use the form below and let us know.

* Required
  • Please post the headline of the story or the title of the video with the error.

  • Please post exactly what was wrong with the story.

  • Please indicate your source for the correct information.

  • Yes

    No

  • This will only be used to contact you if we have a question about your submission, it will not be used to identify you or be published.

  • Cancel

Having problems with the form?

Contact Us Directly
  • Print

You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is be a Winnipeg Free Press print or e-edition subscriber to join the conversation and give your feedback.

You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is be a Winnipeg Free Press print or e-edition subscriber to join the conversation and give your feedback.

Have Your Say

New to commenting? Check out our Frequently Asked Questions.

Have Your Say

Comments are open to Winnipeg Free Press print or e-edition subscribers only. why?

Have Your Say

Comments are open to Winnipeg Free Press Subscribers only. why?

The Winnipeg Free Press does not necessarily endorse any of the views posted. By submitting your comment, you agree to our Terms and Conditions. These terms were revised effective April 16, 2010.

letters

Make text: Larger | Smaller

LATEST VIDEO

Stuart Murray announces musical RightsFest for CMHR opening weekend

View more like this

Photo Store Gallery

  • Aerial view of Portage and Main, The Esplanade Riel, Provencher Bridge over the Red River, The Canadian Museum for Human Rights and The Forks near the Assiniboine River, October 21st, 2011. (TREVOR HAGAN/WINNIPEG FREE PRESS) CMHR
  • Ruth Bonneville Winnipeg Free Press January 18, 2011 Local Standup -

View More Gallery Photos

Poll

Should the city grant mosquito buffer zones for medical reasons only?

View Results

View Related Story

Ads by Google