Wind not only reason for stadium delay
Contractor accuses firm of starting job four months late
As some Winnipeg football fans suspected, high winds over the winter aren't the only reason the new football stadium is behind schedule.
What fans may not have known: Investors Group Field was never expected to be finished before September 2012, never mind in time for tonight's home opener between the Winnipeg Blue Bombers and Edmonton Eskimos.
The general contractor responsible for building the Winnipeg Football Club's new home and the structural-steel subcontractor are blaming each other for the delay in completing the $190-million stadium at the University of Manitoba campus.
When a deal to build the stadium was announced in December 2010, the project was expected to be complete in time for the 2012 season.
But in March 2012, the Winnipeg Football Club revealed construction delays would require the first five games of the season to be played at Canad Inns Stadium. Then in June, the club announced the Bombers would play at their old home for the entire season.
Initially, general contractor Stuart Olson Dominion Construction attributed the delay to high winds that complicated the erection of steel framing for the stadium's roof.
The winds were indeed a factor, Stuart Olson Dominion officials told construction industry analysts in a conference call this week. But they also placed the blame at the feet of Structal Heavy Steel Construction, which they accused of starting the job three to four months late.
Stuart Olson Dominion officials said they are pursuing a claim against Structal -- which they did not identify by name -- for losses incurred as a result of the delay.
The $190-million price tag for Investors Group Field was guaranteed under the terms of the deal between Stuart Olson Dominion and the BBB Stadium, the tax-exempt, non-profit organization set up to develop and build the stadium on behalf of the football club, the U of M Bisons and amateur sport.
Stuart Olson Dominion claims it has incurred additional costs for overtime, heating and insulated winter fencing because it has been forced to resequence other aspects of the construction job. A claim against Structal will be made to recover these costs, officials said.
But a spokesman for Structal said the general contractor is to blame, claiming the foundation for the stadium was not done in time to begin the steel work.
Structal also accused Stuart Olson Dominion of inexperience, claiming there have not been enough managers and superintendents on the site and other components of the stadium project -- including electrical work, plumbing, bowl excavation and the construction of wall partitions -- have yet to be finished, months after the steel work was complete.
Structal claims it is being targeted because it's the largest subcontractor on the job and thus the only company capable of paying up. The steel firm is preparing a claim of its own against Stuart Olson Dominion, its spokesman said.
Structal also alleged the timeline for completing the stadium was unrealistic, claiming only two months were allotted for all trades to complete their work following a July 6 target date for completing the steel work.
Stuart Olson Dominion's schedule called for the stadium to open on Sept. 9, Structal claims.
BBB Stadium chairman Phil Sheegl, the City of Winnipeg's chief executive officer and representative on the organization, confirmed the stadium has always been slated to open in September, although the contractor was supposed to "make every effort" to open it earlier.
BBB Stadium still expects the stadium to be finished in September.
"No one has mentioned to us, in writing, anything different," Sheegl said.
The other members of BBB Stadium are U of M associate vice-president John Alho, provincial representative Vince Barletta and Winnipeg Football Club president and CEO Garth Buchko.
The football club declined interview requests on Wednesday.
"We won't be commenting on this story at this time," spokesman Darren Cameron said.
-- with files from Murray McNeill
Republished from the Winnipeg Free Press print edition July 26, 2012 A4
Fact Check
Have you found an error, or know of something we’ve missed in one of our stories? Please use the form below and let us know.
More Local
- Back to Top
- Return to Local
More Local
(1 of 50 articles for this week)
Keeping the e-party going without the party-crashers
05/25/2013 1:00 AM 0In the beginning, before Facebook got rich from friending and Twitter begat trending tweets, the Free Press created our virtual ...
Poll
Most Popular Local
- MTS becomes takeover target
- Keeping the e-party going without the party-crashers
- Woman drove into river on purpose
- Overnight stabbings probed
- Teachers vote to donate $1.5M to human rights museum
- Doctor charged with sexually assaulting teen at HSC
- Infamous, chronic pedophile declines to seek parole
- PST hike a 'difficult decision' but necessary, NDP official says
- Premier defends PST hike at NDP convention
- Several held in gun sighting
- Man dies after being pulled from vehicle submerged in Winnipeg retention pond
- Flood money paid for CEO's romantic trip
- Crash claims two young women, RCMP say
- Developers to unveil plans for bold downtown tower
- Woman drove into river on purpose
- Police identify slaying victims
- Apple trick on Ellen falls short for city woman
- City's first urban reserve born
- The end of the credit card?
- 2 dead in crash near Portage la Prairie
- Hundreds pitch in to dig out houses damaged, destroyed by Ochre Beach ice floe
- A child-custody catastrophe
- Charleswood deaths being investigated as domestic incident
- Man charged, victims identified in double homicide
- Co-worker 'sick' today? Maybe it's the $17M flu
- Man dies after being pulled from vehicle submerged in Winnipeg retention pond
- '2 minutes after I read the winning numbers, I retired': Winnipeg lotto winner
- Flood money paid for CEO's romantic trip
- Parents, community relieved and elated as missing boy found safe
- No threat from bag found at Winnipeg Square
- Unjust justice: Still no aboriginal court in Manitoba
- MTS becomes takeover target
- SCU pulls Bill 18 petition
- Teachers vote to donate $1.5M to human rights museum
- Keeping the e-party going without the party-crashers
- City's first urban reserve born
- Walk about among 'roos at zoo, mate
- Former CEO 'disappointed' Allstream leaves Manitoba
- Overnight stabbings probed
- You can bet the farm on housebarns
- Developers to unveil plans for bold downtown tower
- Fishing for fashion
- City's first urban reserve born
- Famous city grocer loved job, customers
- Core grocer a challenge: expert
- Flood money paid for CEO's romantic trip
- Grocer Joe Cantor dies at 88
- City chiropractor guilty of beating, sexually assaulting ex-girlfriend
- First Nation celebrates groundbreaking on city's first urban reserve
- North End proud
- Hundreds pitch in to dig out houses damaged, destroyed by Ochre Beach ice floe
- Mental-health patients get own ER
- A child-custody catastrophe
- An uncommon phenomenon
- Steen invests $1M in family entertainment centre
- Developers to unveil plans for bold downtown tower
- Earls on Main going, but new one coming
- Province introduces changes to rules governing landlords, renters
- Crushing blow for amateur sport
- Boost same-sex curricula: union
Ads by Google











You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is register and/or login and you can join the conversation and give your feedback.
Have Your Say
New to commenting? Check out our Frequently Asked Questions.
The Winnipeg Free Press does not necessarily endorse any of the views posted. By submitting your comment, you agree to our Terms and Conditions. These terms were revised effective April 16, 2010.