Major road and bridge projects going smoothly
Winnipeg motorists should be free of barricades on the Disraeli Freeway and Osborne Bridge in less than two months, as all of the city's major road and bridge projects are on schedule this construction season.
The city is overseeing seven road and bridge projects with a price tag of more than $1 million this year. All are on schedule and on budget thanks to relatively dry weather as well as bonus incentives for a pair of the projects, senior city engineers said.
The biggest job of all, the $195-million Disraeli Freeway reconstruction, is slated to open for vehicular traffic on Oct. 19, said Brad Neirinck, Winnipeg's bridge planning and operations engineer. The $17.2-million Osborne Street Bridge reconstruction will open two days earlier, he said.
The largest road project, the extension of Kenaston Boulevard toward the Perimeter Highway, is also on schedule, although it will not be completed until 2013, said Lester Deane, the city's engineering manager. The extension is part of a $54.3-million package of new roads that will service Waverley West.
Here's an update on all seven major projects:
Disraeli Bridge & Overpass
Cost: $195 million
What's up: Reconstruction of the link between downtown and Elmwood involves the completion of the new bridge over the Red River, a new Point Douglas overpass and a bike and pedestrian bridge using existing bridge supports.
The latest: All four lanes of traffic are slated to open on schedule on Oct. 19. The last bit of construction is tricky because part of the new bridge overlaps with the old one and the contractor is required to keep two lanes of traffic open during weekdays. Crews will start to tear down the old bridge in late October. Demolition is expected to take about a month. The bike-and-pedestrian bridge will be completed in 2013.
Waverley West roads
Cost: $54.3 million
What's up: The construction of new roads through south Winnipeg's largest new suburb.
The latest: Contractors are extending Kenaston Boulevard from Bishop Grandin Boulevard to Waverley West's future 'town centre.' Design work is underway on the remaining stretch -- to the Perimeter Highway -- with construction slated to be finished in 2013.
Osborne Street Bridge
Cost: $17.2 million
What's up: Reconstruction of the bridge over the Assiniboine River.
The latest: Little-known fact: The Osborne Street Bridge is two separate bridges. There's a five-cm gap between the two sides of traffic, and crews will work to fill it in with concrete and finish the median before the bridge rehabilitation is complete on Oct. 17. Construction crews have already removed and replaced the top surface of the bridge, widened the sidewalks and the roadway, and installed concrete traffic barriers.
Sturgeon Road Bridge
Cost: $15.2 million
What's up: Replacement of the bridge over Sturgeon Creek.
The latest: Crews are replacing the existing bridge with two twin bridges. Work started in May and crews have demolished part of the eastern portion of the northbound bridge. They're putting in piles and structural concrete so a new northbound bridge can be in place by November.
By next summer, the rest of the southbound half of the bridge will be torn down and a new southbound one will be built. The new bridges will be three metres higher than the old bridge to allow for a creekside bike and pedestrian path.
Dugald Road
Cost: $2.1 million
What's up: Renewal of the westbound lane, from Mazenod Road to Lagimodiere Boulevard.
The latest: Originally slated for an Oct. 8 completion, but is expected to be done in the last week of September.
Fort Street
Cost: $2.1 million
What's up: Renewal of the downtown block between Graham and Portage avenues.
The latest: Following a watermain replacement, work on the road renewal began on Monday. The contractor has until Oct. 19 to complete the work and will receive a bonus of $3,000 per day for every day the work is completed ahead of schedule, up to a maximum of $30,000.
St. James Street
Cost: $1.3 million
What's up: Renewal between Sargent and Wellington avenues.
The latest: Slated to be finished three days early, on Sept. 14. The contractor will receive a bonus of $5,000 per day for each day the work is completed ahead of schedule.
jen.skerritt@freepress.mb.ca bartley.kives@freepress.mb.ca
Republished from the Winnipeg Free Press print edition August 21, 2012 B1
Fact Check
Have you found an error, or know of something we’ve missed in one of our stories? Please use the form below and let us know.
More Local
- Back to Top
- Return to Local
More Local
(1 of 50 articles for this week)
Keeping the e-party going without the party-crashers
05/25/2013 1:00 AM 0In the beginning, before Facebook got rich from friending and Twitter begat trending tweets, the Free Press created our virtual ...
Poll
Most Popular Local
- MTS becomes takeover target
- Keeping the e-party going without the party-crashers
- Woman drove into river on purpose
- Overnight stabbings probed
- Teachers vote to donate $1.5M to human rights museum
- Infamous, chronic pedophile declines to seek parole
- Doctor charged with sexually assaulting teen at HSC
- PST hike a 'difficult decision' but necessary, NDP official says
- Premier defends PST hike at NDP convention
- Several held in gun sighting
- Man dies after being pulled from vehicle submerged in Winnipeg retention pond
- Flood money paid for CEO's romantic trip
- Crash claims two young women, RCMP say
- Developers to unveil plans for bold downtown tower
- Woman drove into river on purpose
- Police identify slaying victims
- Apple trick on Ellen falls short for city woman
- City's first urban reserve born
- The end of the credit card?
- 2 dead in crash near Portage la Prairie
- Hundreds pitch in to dig out houses damaged, destroyed by Ochre Beach ice floe
- A child-custody catastrophe
- Charleswood deaths being investigated as domestic incident
- Man charged, victims identified in double homicide
- Co-worker 'sick' today? Maybe it's the $17M flu
- Man dies after being pulled from vehicle submerged in Winnipeg retention pond
- '2 minutes after I read the winning numbers, I retired': Winnipeg lotto winner
- Flood money paid for CEO's romantic trip
- Parents, community relieved and elated as missing boy found safe
- No threat from bag found at Winnipeg Square
- Unjust justice: Still no aboriginal court in Manitoba
- MTS becomes takeover target
- SCU pulls Bill 18 petition
- Teachers vote to donate $1.5M to human rights museum
- Keeping the e-party going without the party-crashers
- City's first urban reserve born
- Walk about among 'roos at zoo, mate
- Former CEO 'disappointed' Allstream leaves Manitoba
- Overnight stabbings probed
- You can bet the farm on housebarns
- Developers to unveil plans for bold downtown tower
- Fishing for fashion
- City's first urban reserve born
- Famous city grocer loved job, customers
- Core grocer a challenge: expert
- Flood money paid for CEO's romantic trip
- Grocer Joe Cantor dies at 88
- City chiropractor guilty of beating, sexually assaulting ex-girlfriend
- First Nation celebrates groundbreaking on city's first urban reserve
- North End proud
- Hundreds pitch in to dig out houses damaged, destroyed by Ochre Beach ice floe
- Mental-health patients get own ER
- A child-custody catastrophe
- An uncommon phenomenon
- Steen invests $1M in family entertainment centre
- Developers to unveil plans for bold downtown tower
- Earls on Main going, but new one coming
- Province introduces changes to rules governing landlords, renters
- Crushing blow for amateur sport
- Boost same-sex curricula: union
Ads by Google











You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is register and/or login and you can join the conversation and give your feedback.
Have Your Say
New to commenting? Check out our Frequently Asked Questions.
The Winnipeg Free Press does not necessarily endorse any of the views posted. By submitting your comment, you agree to our Terms and Conditions. These terms were revised effective April 16, 2010.