Premier Greg Selinger once said Manitoba Hydro's partnerships with First Nations "yield phenomenal social licence."

Indeed, the fact five hydro-affected First Nations have joined Hydro in development of new dams has lent moral clout to the utility's ambitious plans.

That moral high ground is eroding. Hydro's "new era" of northern dealings is in trouble as it sits on the brink of committing to the $6.5-billion Keeyask project.

Phase one of the new era was the Wuskwatim Dam, which went into operation in 2012. Hydro offered Nisichawayasihk Cree Nation the option to purchase a 33 per cent share in the dam.

Hydro, government and NCN said the partnership held great promise for the future. In 2011, a band councillor said Wuskwatim would earn up to $40 million a year, a third of it going to NCN.

It hasn't worked out that way. According to Hydro, NCN's share of Wuskwatim's losses will total $24 million for the past fiscal year and a combined $134 million over the first decade of the dam's operation.

That's worth another take. The community of 4,800 people, 80 kilometres west of Thompson, has invested $108.4 million -- most of it borrowed from Hydro -- in a venture that is predicted to lose the community $134 million over 10 years.

Welcome to the new era.

Hydro has said NCN will not actually have to pay the utility for its share of annual losses, as the original agreement would have required. Hydro will cover those losses for now, incorporating them into its long-term financial agreement with NCN, essentially borrowing from NCN's future profits to pay for present losses.

One way or another, NCN is stuck with the losses.

Hydro is also stuck with its share of losses, but that's different. It simply passes them on to ratepayers. But NCN doesn't have the option of raising anyone's rates because its revenue stream is based on export prices, not domestic rates.

To be fair, NCN's benefits from Wuskwatim also included a $5.7-million adverse-effects settlement as well as training and employment opportunities. Hydro and governments spent $60 million on a training program centred at NCN. About one-third of person-hours of employment during the construction of the dam went to NCN members. Less impressive were the turnover rate of 41 per cent and the average duration of employment: eight months.

That was the construction boom. At last report, only four NCN members work at long-term jobs at the dam.

Now four other First Nations -- Tataskweyak, York Factory, Fox Lake and War Lake -- are lined up for similar "new era" agreements on the proposed $6.5-billion Keeyask dam. They can purchase a combined stake of up to 25 per cent in the dam if they come up with about $375 million.

The "Keeyask Cree Nations" negotiated another option that would amount to a roughly two per cent stake in the dam, with a guaranteed minimum annual payment whether or not the dam makes money. Of course, the payments to the communities would be far less than the windfall once touted under the 25 per cent share.

The current assumption is the KCNs will choose this "preferred" option, providing the First Nations a combined $5 million annually in the early years of the dam.

These communities agreed to the dams based in part on the bold talk of hefty profits and a prosperous future. But the deals were negotiated before the recession and the spike in shale-gas production sank the export market, which is key to the profitability of the dams.

How would they vote today?

What happens if they toss their partnership agreements in the murky old-era waters of the Nelson River, either now or in a decade? Legally they can't, but morally who could fault future generations for defying this form of partnership?

Hydro's First Nations partners used to defend the new dams vehemently.

No one talks that way anymore. KCN leaders are contractually required to speak in favour of the dams, but the vigour is largely gone. And the behind-the-scenes grumbling is leaking out.

That's not what Hydro and Selinger want to hear after paying northern First Nations $241 million for negotiation costs since 1999.

Selinger said last year Hydro's "legacy of bitterness" in the north has been replaced by a spirit of partnership. Sadly, the new era of dams may exacerbate the bitterness rather than heal it.

Add that social risk to the massive financial risk of Keeyask, and Manitobans should ask whether Hydro has general societal approval to proceed with the dam.

By July, when Hydro wants to start building Keeyask, our utility is likely to have an Environment Act licence and a Water Power Act licence for the megaproject. But will it have a legitimate social licence?

 

Will Braun works for the Interchurch Council on Hydropower.

wbraun@inbox.com

Republished from the Winnipeg Free Press print edition April 24, 2014 0

Fact Check

Fact Check

Have you found an error, or know of something we’ve missed in one of our stories?
Please use the form below and let us know.

* Required
  • Please post the headline of the story or the title of the video with the error.

  • Please post exactly what was wrong with the story.

  • Please indicate your source for the correct information.

  • Yes

    No

  • This will only be used to contact you if we have a question about your submission, it will not be used to identify you or be published.

  • Cancel

Having problems with the form?

Contact Us Directly
  • Print

You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is be a Winnipeg Free Press print or e-edition subscriber to join the conversation and give your feedback.

You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is be a Winnipeg Free Press print or e-edition subscriber to join the conversation and give your feedback.

Have Your Say

New to commenting? Check out our Frequently Asked Questions.

Have Your Say

Comments are open to Winnipeg Free Press print or e-edition subscribers only. why?

Have Your Say

Comments are open to Winnipeg Free Press Subscribers only. why?

The Winnipeg Free Press does not necessarily endorse any of the views posted. By submitting your comment, you agree to our Terms and Conditions. These terms were revised effective April 16, 2010.

letters

Make text: Larger | Smaller

LATEST VIDEO

Maria Aragon performs new single "Nothing but a Beat"

View more like this

Photo Store Gallery

  • A young goose gobbles up grass at Fort Whyte Alive Monday morning- Young goslings are starting to show the markings of a adult geese-See Bryksa 30 day goose challenge- Day 20– June 11, 2012   (JOE BRYKSA / WINNIPEG FREE PRESS)
  • A Great Horned Owl that was caught up in some soccer nets in Shamrock Park in Southdale on November 16th was rehabilitated and returned to the the city park behind Shamrock School and released this afternoon. Sequence of the release. December 4, 2012  BORIS MINKEVICH / WINNIPEG FREE PRESS

View More Gallery Photos

Poll

Should panhandling at intersections be banned?

View Results

View Related Story

Ads by Google