Government to reap more than $200 million a year from Hydro expansion

  • Print
Premier Greg Selinger, second from left, on tour of Wuskwatim dam.

MIKE DEAL / WINNIPEG FREE PRESS ARCHIVES Enlarge Image

Premier Greg Selinger, second from left, on tour of Wuskwatim dam. Photo Store

Graham Lane, past chairman of Manitoba's Public Utilities Board, begins a weekly column today that will address public policy and finance issues and how they affect Manitobans. His columns will appear on winnipegfreepress.com, where readers can interact directly with Mr. Lane in our comments section.

The NDP government is pressuring (if not bullying) Manitoba Hydro into pursuing a massive $20-billion-plus expansion of its transmission and hydroelectric generation infrastructure, a plan based on the premise of profitable sales of excess power to American utilities.

Despite a calamitous decline in the price Hydro receives for its non-firm electricity export sales, sales that have represented more than 60 per cent of total export sales, and seemingly endless increases in the projected capital cost of the plan, Hydro has already spent or committed $2 billion, entered into partnership agreements with northern First Nations, hired hundreds of new employees and signed contracts or term sheets (in-principle contracts) with American utilities.

Even the economic disaster that is Hydro's Wuskwatim dam -- costs double and sales prices half that expected (the almost $2-billion cost is additional to the $20-billion major development plan) -- has failed to bring about a pause.

It is critical the government and Hydro identify major risks ranging from further increases in construction-cost estimates, through droughts and interest-rate increases to a possible tripling of rates for consumers, and more, ahead of a proper, full and expert public review of the economics of the scheme, and serious consideration of less costly, less risky options.

So why is the NDP government pursuing a plan identified as being risky from so many standpoints? Why has the government ignored the major economic and market changes that have occurred since the plan was developed more than five years ago?

Follow the money is an approach often used to discern motives. And, likely to no one's surprise, if the government's plans for Hydro are implemented, the biggest winner will be it, the NDP government.

First and most important, proceeding to conclusion of the plan will not further risk the government's own financial situation. The government has "no skin in the game," having made no financial investment whatsoever in Hydro or its development plan.

Only Hydro ratepayers have skin in the game, as any future revenue deficiency will have to be met by them, and many already have trouble paying their bills.

(Approximately 35 per cent of consumers rely on electricity for heating; unlike the situation in Saskatchewan, gas distribution in Manitoba through Centra Gas, a subsidiary of Manitoba Hydro, is quite limited.)

As it stands, Hydro forecasts consumer electricity rates will almost certainly go up by four per cent, twice the expected rate of inflation, each year for the next 20 years.

Given what is known and can be drawn from past experiences with Hydro forecasts, there is a high risk that, in the end, rate hikes will be much higher than Hydro now forecasts. I stand by my earlier forecast of an eventual tripling of rates.

While ratepayers may worry about future rate hikes, the government, with no skin in the game, awaits a windfall.

For every dollar borrowed by Hydro, the government, which guarantees debt repayment, gains an additional one cent a year -- $20 billion of additional borrowings means $200 million more, annually, for the government's coffers.

For every dollar increase in Hydro's capital base (which includes retained earnings and borrowings), additional capital tax revenue flows annually to the government. For every kilowatt produced through water flow, for every dam the water flows through, government will receive additional water-rental fees.

There is even more annual revenue for government to flow from Hydro's massive construction plan -- individual income taxes from a swollen personnel complement, increased corporate taxes from suppliers to Hydro and, let us not forget, annual revenue from the recently increased retail sales tax.

The construction is scheduled to go into high gear in 2015-16 providing jobs and money to the economy (albeit borrowed money); coincidentally, this will be the time of the next provincial election.

Hundreds of millions, accumulating to billions of dollars over the lengthy planned construction period, will flow into the government's Consolidated Fund, helping the government to reduce what would otherwise be an even steeper climb toward a balanced budget.

If the government's plan is actualized, the money to flow from Hydro to the government will exceed anything it can expect to realize from lotteries, liquor and the gas-and-tobacco tax combined. Better still for government, at least from an electoral-process perspective, whatever rate hikes are required to keep Hydro in the black will be met by ratepayers, not government. And while the government will rake in billions as the projects are undertaken, Hydro will defer the costs until the assets are in service, allowing the utility to record profits.

Due to the cost deferrals, Manitoba ratepayers will not be asked to pick up the full tab until after two elections.

Postscript: Given the expenses and commitments made to date, the government's risk is to stop and not proceed any further, which would trigger write-offs and liabilities in Hydro's books. Those losses would drive up the province's own deficit, making it even harder for the government to meet its latest promise, that being to balance its own books for 2016-17.

Of course, the ratepayers would, in the end, be on the hook for that, too. A no-win situation for ratepayers is in sight.

 

Graham Lane is a retired chartered accountant who served as the chairman of the Public Utilities Board from to 2004 to 2012.

 

Whose interests are being served by Hydro expansion? Join the conversation in the comments below.

Republished from the Winnipeg Free Press print edition October 9, 2013 A9

History

Updated on Wednesday, October 9, 2013 at 6:58 AM CDT: changes headline, replaces photo, adds question for discussion

Fact Check

Fact Check

Have you found an error, or know of something we’ve missed in one of our stories?
Please use the form below and let us know.

* Required
  • Please post the headline of the story or the title of the video with the error.

  • Please post exactly what was wrong with the story.

  • Please indicate your source for the correct information.

  • Yes

    No

  • This will only be used to contact you if we have a question about your submission, it will not be used to identify you or be published.

  • Cancel

Having problems with the form?

Contact Us Directly
  • Print

You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is be a Winnipeg Free Press print or e-edition subscriber to join the conversation and give your feedback.

You can comment on most stories on winnipegfreepress.com. You can also agree or disagree with other comments. All you need to do is be a Winnipeg Free Press print or e-edition subscriber to join the conversation and give your feedback.

Have Your Say

New to commenting? Check out our Frequently Asked Questions.

Have Your Say

Comments are open to Winnipeg Free Press print or e-edition subscribers only. why?

Have Your Say

Comments are open to Winnipeg Free Press Subscribers only. why?

The Winnipeg Free Press does not necessarily endorse any of the views posted. By submitting your comment, you agree to our Terms and Conditions. These terms were revised effective April 16, 2010.

letters

Make text: Larger | Smaller

LATEST VIDEO

Steeves wants to divert BRT cash to rec centres

View more like this

Photo Store Gallery

  • BORIS MINKEVICH / WINNIPEG FREE PRESS  070527 The 21st Annual Teddy Bears' Picnic at Assiniboine Park. The Orlan Ukrainian Dancers perform on stage.
  • A pelican comes in for a landing Wednesday afternoon on the Red River at Lockport, Manitoba - Standup photo- June 27, 2012   (JOE BRYKSA / WINNIPEG FREE PRESS)

View More Gallery Photos

About Graham Lane

Graham Lane is a retired chartered accountant who worked in the public and private sectors for 50 years, concluding his career as chairman of the Manitoba Public Utilities Board.

He has also held key positions at Credit Union Central, Public Investments of Manitoba, the Manitoba Public Insurance Corp., the University of Winnipeg, and the Manitoba Worker's Compensation Board.

Before gaining his CA designation in Quebec, he was third in Canada in the then-national intermediate examination. He has a diploma in business administration from the University of Western Ontario and has served on numerous charitable and service boards.

Poll

Do you think food-security issues are an important topic to address during this mayoral campaign?

View Results

View Related Story

Ads by Google