The Selinger government is in a race to lower Lake Manitoba before next spring as the cost of fighting this year's flood in western Manitoba almost doubles what was seen in the 1997 Red River deluge.
Hey there, time traveller! This article was published 4/7/2011 (3973 days ago), so information in it may no longer be current.
The Selinger government is in a race to lower Lake Manitoba before next spring as the cost of fighting this year's flood in western Manitoba almost doubles what was seen in the 1997 Red River deluge.
Work to pick a route to transport water from Lake Manitoba into Lake Winnipeg has already started, with the province hoping to have a ditch dug by Jan. 1 so it can lower Lake Manitoba by more than four feet over the winter, officials said Monday.
TIM SMITH/BRANDON SUN
Souris's damaged suspension bridge is seen from the air on Monday.
"We see this as an emergency outlet and may have to be constructed under a provincial state of emergency," Steve Topping, the province's chief flood-fighter and head of operations for Manitoba Water Stewardship, said Monday. "The CEAA (Canadian Environmental Assessment Agency) and also the provincial environmental-licensing processes would not have to be gone through under a provincial state of emergency. They will be fast-tracked."
News the province is working quickly to ease the pressure on the flooded Lake Manitoba, likely through a mini-floodway from Lake St. Martin to Lake Winnipeg, was mostly welcomed by those who live or have cottages on Lake Manitoba, but also condemned because it wasn't happening fast enough. Lake Manitoba's water level is at 817.13 feet above sea level -- its highest ever. The lake is as high as it is partly due to so much water flowing into it this year through the Portage Diversion from the Assiniboine River.
Lake Manitoba empties into Lake St. Martin, which then empties in Lake Winnipeg via the Dauphin River. One plan under consideration is a controlled diversion that parallels the Dauphin River.
"I'm just wildly disappointed," flooded-out Langruth rancher Tom Teichroeb said. "This is just beyond stupid. There is just no reason why it should take until January of next year to get the lake down. They are drowning people. It's their obligation to get their (act) together and get this damn lake down."
Teichroeb, chairman of the Lake Manitoba Flood Rehabilitation Committee, also said Premier Greg Selinger's announcement Monday on increased compensation for flood victims is nothing more than pandering to urban voters.
"That's not the real picture," he said. "When you're on this side of it, it's pretty pathetic."
Don Clarkson, of the Association of Lake Manitoba Stakeholders, said he hopes the province starts work on the drainage outlet -- there is no cost estimate for it yet -- as soon as possible. The province has two engineering firms studying possible routes.
"Any improvement is good," Clarkson said. "The lake is not going down any time soon. It's still coming up."
Clarkson was one of hundreds of people evacuated in late May because of a destructive storm on Lake Manitoba. His home at Delta Beach has foundation damage and he likely won't be allowed to return for a year.
"We actually look like a ghost town more than anything. Here it's summer and there is nobody sitting out there enjoying it."
Clarkson and Twin Lakes Beach cottager Jeff Douglas said they're concerned the province's new compensation plan is too vague. It doesn't recognize the value of cottages wrecked during the storm or if compensation payments are considered income by the Canada Revenue Agency.
"This is still woefully short when they were the ones at fault," Douglas said.
Selinger's announcement comes as this year's flood bill almost doubles what was spent fixing and flood-proofing the Red River Valley following the 1997 flood. The cost of this year's flood in western Manitoba will top $550 million and could climb higher depending on the weather and the extent of flooding on the Souris River.
The cost of fighting and damages from the 1997 Red River flood were about $280 million.
The Free Press | Newsletter
Winnipeg Gardener
What you need to know now about gardening in Winnipeg. A monthly email from the Free Press with advice, ideas and tips to keep your outdoor and indoor plants growing.
Ottawa covers a large portion of compensation and flood-proofing costs.
Selinger said while costs are mounting, the province can't worry about the impact to its own books, which are in deficit under the government's five-year economic recovery plan.
"The fact of the matter is that people are suffering," he said. "Incomes have been lost. Homes have been lost. Communities are at risk of losing their economic base. The faster we help people rebuild their homes, the faster we help communities recover, the better it will be for the economy."
Progressive Conservative Leader Hugh McFadyen said the uncertainty in Selinger's flood-compensation plan is a problem.
"We support urgent action to address dangerously high lake levels," McFadyen said. "We are concerned about the vagueness."
bruce.owen@freepress.mb.ca
Here's the deal on compensation
The province's revamped flood-compensation package includes:
- Under the Disaster Financial Assistance Program, the maximum payout will increase to $240,000 from $200,000. The province will also fully waive the 20 per cent co-payment for permanent flood-proofing. Cottages and recreational property do not qualify for DFA.
- The province is also expanding the current coverage for homeowners who undertake permanent flood protection for their homes, businesses or farms under a new $75-million mitigation program and is extending coverage to cottages. The program is provincewide and includes Lake Manitoba, Lake Winnipeg, Dauphin Lake, Oak Lake and other affected properties on rivers and lakes. Permanent flood protection includes building dikes, raising properties or moving residences on properties.
Homes, businesses and farms will be eligible for up to 86 per cent in government funding for projects up to $100,000. Owners will be eligible to receive $86,000 in government funding on projects that cost $100,000. Owners will be responsible for 14 per cent of costs up to $100,000 and 100 per cent of costs above $100,000.
Cottage owners will be eligible for 86 per cent in government funding for projects up to $40,000. Owners will be responsible for 14 per cent of costs up to $40,000 and 100 per cent of costs above $40,000. Lake Manitoba residents can also apply for funding of up to $20,000 or 90 per cent of the costs of moving or raising homes and cottages in the flood inundation zone.
-- On property taxes, the province has set aside $2.5 million to help families whose properties have been damaged or destroyed by flooding and ensure municipalities maintain a revenue stream to continue running their operations. School and municipal taxes for homes and cottages will be covered by the Manitoba government from the time the properties were affected by flooding. The payment will be made to the municipality and applied to the account of affected property owners.
* * *
Under the Lake Manitoba Financial Assistance Program, the maximum payout for permanent homes will increase to $270,000 from $200,000. The province will also fully waive the 10 per cent co-payment for permanent flood-proofing. The $90,000 available for cottage owners to support structural damage costs does not change.
The Winnipeg Free Press invites you to share your opinion on this story in a letter to the editor. A selection of letters to the editor are published daily.
To submit a letter:
• fill out the form on this page, or
• email letters@freepress.mb.ca, or
• mail Letters to the Editor, 1355 Mountain Avenue, Winnipeg, Manitoba, R2X 3B6.
Letters must include the writer’s full name, address, and a daytime phone number. Letters are edited for length and clarity.