Arlington Bridge troubles span nearly a century First structural repairs needed in 1931 when acrid smoke ate away at bridge deck

The Arlington Bridge finds itself in a familiar situation after its sudden closure due to its deteriorating condition. Throughout its history, the bridge has been counted out many times but has managed to survive for more than a century.

Read this article for free:

or

Already have an account? Log in here »

To continue reading, please subscribe:

Subscribe and receive a limited-edition Free Press branded hat or tote.

Digital Subscription

One year of digital access for only $205*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.

To continue reading, please subscribe:

Add Free Press access to your Brandon Sun subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Start now

*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

Hey there, time traveller!
This article was published 01/12/2023 (962 days ago), so information in it may no longer be current.

The Arlington Bridge finds itself in a familiar situation after its sudden closure due to its deteriorating condition. Throughout its history, the bridge has been counted out many times but has managed to survive for more than a century.

Winnipeg was a booming prairie metropolis in the early 1900s divided by one of the country’s busiest rail yards. As its population grew, getting to and from the North End by streetcar, the main form of transport for most citizens, was difficult, as the only streetcar crossing was Main Street.

Alderman Archibald McArthur
Alderman Archibald McArthur

Alderman Archibald McArthur, a Logan Avenue grocer, pushed for the construction of a new bridge that would span the rail yards between what was then called Brown Street in the North End and Brant Street to the south. Many of his city council colleagues were cool on the idea as there were many infrastructure projects competing for dollars in the young city.

To make the bridge more palatable, McArthur convinced his colleagues to approve the construction of the Central Belt Line in 1906. This would have been a second Main Street that that would stretch from the city’s northern limits, down Brown, Brant and Arlington streets, and eventually cross the Assiniboine River via a second span that would connect Wolseley to Crescentwood.

The Central Belt Line was a short-lived idea. Between the time it was approved in 1906 and the end of the decade, the West End and Wolseley had transformed from semi-rural enclaves at the edge of the city to middle-class neighbourhoods and there was little political will to drive a highway through them.

The only remnant of that failed project is that Arlington, Brown and Brant streets were renamed Arlington Street during the planning phase.

Taxpayers weren’t fond of the idea for McArthur’s new bridge either. A money referendum to approve the borrowing of funds to build it was rejected in 1907 and 1908. It was third time lucky in January 1909 after McArthur had it bundled into an omnibus bylaw with other, more popular projects.

A Winnipeg Free Press editorial noted that victory at the ballot box did not mean bridge would materialize: “McArthur is likely to have trouble of his own in bringing about the speedy materialization of this overhead bridge project for there is a strong element in the council, which, while acquiescing to the mandate of the ratepayers as expressed by the recent vote sees no need for haste in expending the $232,000 required to erect the structure.”

As traffic woes on Main Street reached the point of near-constant gridlock, city council was forced to decide on a second streetcar crossing. McArthur, always one step ahead of his colleagues, had already approached the CPR and received preliminary approval from the railway to build over their yards at Arlington Street.

Ruth Bonneville / Winnipeg Free Press 
                                A view of Arlington Street Bridge facing south

Ruth Bonneville / Winnipeg Free Press

A view of Arlington Street Bridge facing south

McArthur’s move saved the city months of negotiations and though a bridge at Arlington Street may not have been the first choice of many on city council, it was the quickest option to get a second streetcar connection to the North End built.

The city called for tenders for the Arlington Street Bridge in May 1910. The William Newman Company won the $55,000 bid to build the piers and the Cleveland Bridge and Engineering Company of Darlingford, England was awarded $205,160 for the superstructure.

Construction soon got underway, but quickly fell behind schedule. Slated to be completed in June 1911, the first cars did not travel over the bridge until February 5, 1912.

The purpose of the Arlington Street Bridge was to be the second streetcar connection to and from the North End, yet no streetcar ever ran over it due to the steep grade of its approaches. Streetcar operators called running a car, particularly down the northern approach to busy Logan Avenue, “suicide.”

For years, the city, the privately owned streetcar company, and the streetcar employee’s union tried to resolve the issue. The city offered to post a full-time crossing guard at Logan Avenue to stop traffic and signal that it was safe to descend. The streetcar company bought some lighter cars fitted with disc brakes for easier stopping. The issue was never resolved, and the streetcar tracks were removed from the bridge in 1928.

The Arlington Bridge was, in the minds of many, a white elephant and its problems just got worse.

The first structural repairs to the bridge were needed in 1931 and another round took place in 1943. The cause of these repairs was the acrid smoke from the rail yards below that ate away at the bridge deck.

In the summer of 1946, the bridge was again closed after failing its annual inspection. The $50,000 repair bill included the installation of blast shields to protect the bridge deck from further corrosion. An exasperated Alderman John Blumberg was quoted by Free Press saying, “The Arlington Street Bridge will always be a bugbear. The sooner the bridge comes down and a modern one goes up, the sooner will the city maintain expenses.”

MIKE DEAL / WINNIPEG FREE PRESS
                                The Arlington Street Bridge passes over the CPR’s Arlington Yards.

MIKE DEAL / WINNIPEG FREE PRESS

The Arlington Street Bridge passes over the CPR’s Arlington Yards.

In 1967, D. I. McDonald, Metro Winnipeg’s streets director, informed city council the bridge was near the end of its functional life and could be closed at any moment. New weight restrictions imposed on the bridge rerouted trucks and buses and a 15 mile-per-hour speed limit was imposed. North End city councillor Joe Zuken called the span a “crippled bridge with weight restrictions,” adding, “such a bridge is a disgrace to a modern urban centre.”

Fortunately for the city, a new bridge project was on the horizon.

The Sherbrook-McGregor Overpass would connect those two streets and do away with the need for both the Arlington Street and Salter Street bridges. The high cost of construction and opposition from community members who did not want its highway-style approaches running through their neighbourhood delayed the project. By the late 1970s, the overpass project was dead.

As approval of the Sherbrook-McGregor Overpass bogged down, the city had to decide about the future of the Arlington Bridge. It chose to close it for two months in 1972 for extensive renovations. When it reopened, the truck and bus restrictions remained in place.

Another 1970s-era project that could have had a great impact on the future of the Arlington Bridge was the relocation of the CPR yards to the outskirts of Winnipeg.

MIKE DEAL / WINNIPEG FREE PRESS
                                The Arlington Bridge crosses over the CP Arlington Yards in this aerial image. 160628 - Tuesday, June 28, 2016

MIKE DEAL / WINNIPEG FREE PRESS

The Arlington Bridge crosses over the CP Arlington Yards in this aerial image. 160628 - Tuesday, June 28, 2016

Rail yard relocation was first mentioned in a 1972 federal government report on the changing nature of the railway industry in urban centres. Two years later, the federal urban affairs minister toured the area and said the federal government could cover up to half the cost of the project. He told the Free Press, “The relocation could change the whole social fabric of the city by getting rid of the expression ‘wrong side of the tracks.’”

The city did not act quickly enough to take the federal government up on its offer and preliminary talks about moving the rail yards came to an end in 1975. Fifty years later, the possibility of relocating the rail yards is still talked about as an alternative to a new Arlington Bridge.

In 2018, the City of Winnipeg began public consultations about the replacement of the Arlington Bridge. Project advisory committee members were informed by the city that the bridge was again coming to the end of its functional life and would be decommissioned in 2024. It made it to within six weeks of that target before being unceremoniously and indefinitely closed on November 21, 2023.

A design for the new Arlington Bridge was approved by city council in 2019 but there is no timeline or funding in place for its construction, putting its fate in limbo once again.

What does the future hold for the current Arlington Bridge? If history is any indication, it might not be surprising to see it still standing a decade from now. It is a survivor that has managed to outlive generations of critics to become one of the oldest bridges in the city.

Report Error Submit a Tip

More Stories

Fringe reviews #11: Our princess is in another theatre

Free Press review team 10 minute read Preview

Fringe reviews #11: Our princess is in another theatre

Free Press review team 10 minute read Saturday, Jul. 18, 2026

'80s Commercials, Alexander Mantia's Zucchini Club, The Ballad of Isobel Gunn, Fission, Flunked, Fringe Family Fun Show, One More Time, A Savage Love Story, Story Story Lie, The (Un)Official (Un)Researched History, Unresolved.

Read
Saturday, Jul. 18, 2026

Animal rescue worker reportedly killed in dog attack

Morgan Modjeski 4 minute read Preview

Animal rescue worker reportedly killed in dog attack

Morgan Modjeski 4 minute read Friday, Jul. 17, 2026

Police are investigating after a woman died on the Sandy Bay First Nation, reportedly after being attacked by dogs.

The woman was identified by family as 37-year-old Amanda Nobiss.

“It’s just disbelief,” said Sherri Nobiss, her mother, in a phone call. Her family is devastated by the loss. “You just want to know what has happened.”

She said Amanda was a dedicated animal advocate who was volunteering with K9 Advocacy Manitoba in the community at the time. Amanda, who was from Winnipeg, is pictured with a dog in almost all of her photos on social media.

Read
Friday, Jul. 17, 2026

STARS moves to Brandon to fill gap after Dauphin hospital closes

Nicole Buffie 2 minute read Preview

STARS moves to Brandon to fill gap after Dauphin hospital closes

Nicole Buffie 2 minute read 2:04 PM CDT

STARS air ambulance’s operations are being temporarily relocated from Winnipeg to Brandon to help out in the region after an area hospital was forced to shutter due to flooding.

The Prairie Mountain Health region said the move is expected to reduce transport and response times for patients requiring rapid escalation to higher levels of care.

The Dauphin Region Health Centre was forced to evacuate its patients and close on July 1 after the region experienced severe flooding.

The hospital’s basement flooded and power was knocked out, which caused significant damage to the facility’s HVAC system. Fifty-four patients were sent to nearby health centres, including 24 patients who were transferred to the Brandon hospital.

Read
2:04 PM CDT

Longtime CNIB volunteer says he’s still amazed at people’s resilience

Tiago Resko 8 minute read Preview

Longtime CNIB volunteer says he’s still amazed at people’s resilience

Tiago Resko 8 minute read 6:00 AM CDT

After decades of helping blind and partially sighted Manitobans live their dreams, Ken Curtis says he’s still inspired by the courage and strength the clients of the CNIB demonstrate every day.

“For me, they’re just the most unbelievable people in the world,” he said.

Curtis has been volunteering for 40 years with the Canadian National Institute for the Blind, which helps blind and partially sighted people find innovative ways to achieve their goals.

“The bravery that these people show in terms of what they’ve accomplished and who they are and their positive attitude, I just fell in love with all of our clients,” he said. “And of course many of them are good friends now.”

Read
6:00 AM CDT

Bombers battle back to beat Redblacks in OT

Taylor Allen 6 minute read Preview

Bombers battle back to beat Redblacks in OT

Taylor Allen 6 minute read Updated: 9:44 AM CDT

OTTAWA — For three and a half quarters, it looked like it was going to be a night Dru Brown would want to forget.

And in some ways, he still might want to erase Sunday from his memory because it wasn’t overly pretty.

But in the end, Brown got his revenge and the Winnipeg Blue Bombers recovered from a sloppy start to escape the nation’s capital with a 36-34 overtime victory over the Ottawa Redblacks.

The game literally went down to the wire as it remained tied after two overtime mini-games and had to be decided by alternating two-point conversion attempts from the 3-yard line — a first in CFL history as the new overtime format was introduced this season.

Read
Updated: 9:44 AM CDT

Fringe reviews #15: Button-mashing mayhem

Free Press review team 10 minute read Preview

Fringe reviews #15: Button-mashing mayhem

Free Press review team 10 minute read Yesterday at 3:36 PM CDT

Babel, Chase Padgett, Dirk Darrow, The Glass Between Us, K-Tel Demon Hunters, Mr. Richard, Penny Ashton, Grant Canyon, Rocky Horror Show, Wisecracks for Weirdos

Read
Yesterday at 3:36 PM CDT