New Ontario Science Centre at Ontario Place to open in 2029, auditor general says

Advertisement

Advertise with us

TORONTO - The timeline for opening a permanent new Ontario Science Centre appears to have been delayed, with infrastructure officials telling the auditor general's office the centre is expected to be up and running in 2029.

Read this article for free:


By clicking the button above, an account will be created and you will begin to receive some of our recommended newsletters. You may opt out of any newsletter by visiting your Email and Communication Preferences page or by clicking "unsubscribe" at the bottom of any email.

or

Already have an account? Log in here »

To continue reading, please subscribe:

Digital Subscription

One year of digital access for only $1.44 a week*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*Billed as $5.77 plus GST every four weeks. After 52 weeks, price increases to the regular rate of $19.95 plus GST every four weeks. Offer available to new and qualified returning subscribers only. Cancel any time.

To continue reading, please subscribe:

Add Free Press access to your Brandon Sun subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Start now

*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

Hey there, time traveller!
This article was published 19/12/2024 (674 days ago), so information in it may no longer be current.

TORONTO – The timeline for opening a permanent new Ontario Science Centre appears to have been delayed, with infrastructure officials telling the auditor general’s office the centre is expected to be up and running in 2029.

When Premier Doug Ford announced last year the planned move for the attraction, from its east Toronto location to a redeveloped Ontario Place on the city’s waterfront, the science centre said the new facility would open in 2028.

In June, when the government announced the abrupt closure of the science centre over structural concerns with the roof, its press release said the Ontario Place facility would open “as early as” 2028.

A woman waits outside the new temporary pop-up Ontario Science Centre located in Sherway Gardens mall in Toronto, Tuesday, Dec. 3, 2024. THE CANADIAN PRESS/Nathan Denette

A woman waits outside the new temporary pop-up Ontario Science Centre located in Sherway Gardens mall in Toronto, Tuesday, Dec. 3, 2024. THE CANADIAN PRESS/Nathan Denette

Now, according to a report earlier this month from Ontario’s auditor general Shelley Spence on the Ontario Place redevelopment, “the new building is expected to open in 2029.”

That information was provided to the auditor general’s office by Infrastructure Ontario, a spokesperson for the auditor said.

Jason Ash, co-chair of the group Save Ontario’s Science Centre, said it’s a shame that there will be no permanent Ontario Science Centre for at least an extra year.

“It’s really a whole generation of Ontario children who are not going to have access to world-class science education that the Ontario Science Centre has provided for 55 years,” he said.

“Simply put, the Ontario Science Centre was unique in that the majority of its business actually came from Ontarians, with tourism coming in second place. So Ontario kids aren’t being served and tourists are not going to get a great experience either in the meantime.”

Two requests for comment from Infrastructure Minister Kinga Surma went unanswered, with a spokesperson ultimately replying to a third by saying she would not be responding.

“Due to the request submitted by the Leader of the Official Opposition to the Integrity Commissioner on October 16th, 2024, Minister Kinga Surma has been asked not to comment and will respect the process at this time,” Ash Milton wrote.

Milton’s reply came after Surma answered at least a dozen questions in question period on the auditor general’s Ontario Place redevelopment findings.

NDP Leader Marit Stiles’ integrity complaint focused largely on terms and negotiations that led to a 95-year lease for Therme to build and operate a spa and waterpark at Ontario Place, but also alleges “irregularities” with the plan to relocate the science centre.

Stiles suggests, based on information previously uncovered last year by the auditor general, that the government wanted to have the science centre at Ontario Place and integrate parking promised to Therme with the science centre building in order to dispel public concerns over the project.

“This is yet another expensive project that nobody asked for – with a plan that no one is buying,” Stiles wrote in a statement this week.

“We could have revitalized the existing Science Centre for a fraction the cost. Ford and Surma boasted about the new Science Centre opening in 2028, but that sounds like more false promises from a flailing government.”

A spokesperson for Infrastructure Ontario said the procurement process for the new centre continues, with the request for proposals stage expected to wrap up next fall.

A firm date for the completion of construction will be posted once a contract is awarded, and the opening date will depend on the centre’s timeline for moving into the new building, Karen Evans said in an email.

“The overall plan for delivering the vision remains unchanged,” she said.

That audit found that it will now cost more for the government to build a new Ontario Science Centre at Ontario Place than it would have to maintain the site it abruptly closed earlier this year.

The cost estimate for building and maintaining a new science centre at Ontario Place has increased by nearly $400 million from the government’s spring 2023 business case for relocating it, the auditor said, meaning it will cost approximately $1.4 billion — higher than the $1.3-billion estimate for maintaining the attraction at its east Toronto location.

The increase is due to higher design and construction costs, life cycle and maintenance costs, and ancillary costs that have added up because of changes to the scope of the planned building and about $61 million in cost escalations, Spence wrote.

Michael Lindsay, at the time the president and CEO of Infrastructure Ontario, said he didn’t agree that building a new science centre will cost more than rehabilitating the old one, noting that project would also be facing inflationary price increases.

Lindsay provided some reasoning for possible delays in a briefing on the day the science centre was closed.

“The language … (of “as early as” 2028) probably just reflects the realities of procurement and construction,” he said.

“We’re going to be talking to our counterparties through the procurement about what it would take to construct a new science centre, how long that might be, and so I think the plan remains the plan. That language probably just points at the reality that further conversation with our market is coming about what it’s going to take to both procure and then build the new science centre.”

Ontario is planning to have a temporary science centre open in the interim, but has not provided any public updates on that process since it issued a request for proposals in June.

That RFP showed the province is looking for retail or commercial space of about 50,000 to 100,000 square feet — much smaller than the original building’s 568,000 square feet – with a start date of “no later than” Jan. 1, 2026.

The RFP also showed that the province wants a lease of up to five years for the temporary space, plus three options to extend the lease for one year each, which would allow the government to operate a science centre in a temporary home until 2034, Ash said.

The science centre is currently operating two pop-up exhibits at Harbourfront Centre and the Sherway Gardens mall in Toronto.

This report by The Canadian Press was first published Dec. 19, 2024.

Report Error Submit a Tip

More Stories

Hutterite colonies embrace the manufacturing business – while staying faithful to their way of life

Gabrielle Piché 13 minute read Preview

Hutterite colonies embrace the manufacturing business – while staying faithful to their way of life

Gabrielle Piché 13 minute read Thursday, Oct. 22, 2026

Tucked away at Oak Bluff Hutterite Colony, past rows of communal housing and farm buildings, Aaron Maendel tinkers in a laboratory.

Black-and-white sheets smeared with grey-test formulas cover a counter. A Thermotron — a refrigerator-looking machine — is powered off but standing by to simulate any desired temperature.

Maendel moves to a worktop littered with partly full mixing cups. He pulls out a small, rectangular sample — a sheet showing the drying time of his new fixation, floor coatings.

“Very simple, actually. Very simple machine. Drags a stick through the mud,” Maendel says.

Read
Thursday, Oct. 22, 2026

Building generational equity

Joel Schlesinger 6 minute read Preview

Building generational equity

Joel Schlesinger 6 minute read 2:02 AM CDT

Ayobimpe Omisore is a Winnipeg single mother of four who knows all too well about working just to make the rent.

A little more than a year ago, she was struggling to pay $2,400 a month for a two-bedroom unit in St. Norbert.

She picked up extra shifts whenever she could as a health-care aide to keep up with the costs.

“I was lamenting about it at work one day, and a colleague said, ‘If you’re paying this much on rent, I think you can afford a mortgage,’” says Omisore, who came to Canada four years ago from Nigeria where she worked as a logistics manager.

Read
2:02 AM CDT

Builder beefs up security after string of blazes

Morgan Modjeski 3 minute read Preview

Builder beefs up security after string of blazes

Morgan Modjeski 3 minute read Updated: Yesterday at 9:36 AM CDT

A Winnipeg builder said he’s had to beef up security around his developments after one of his projects sustained significant damage Wednesday in suspected arson cases.

Read
Updated: Yesterday at 9:36 AM CDT

Garden grandees

Colleen Zacharias 7 minute read Preview

Garden grandees

Colleen Zacharias 7 minute read 2:00 AM CDT

The last few weeks have been a whirlwind of activity at Robert and Susan Choquette’s spacious rural property in Oakbank. They have been busy preparing multiple gardens for winter, digging and storing scores of canna rhizomes, and bringing tender plants indoors for the winter.

The couple’s stunning property was featured on this year’s Gardens of Distinction tour by Nature Manitoba which was held on July 4.

Visitors were wowed by the abundant plantings of flowering annuals in a long, curved border at the entrance to the garden. A mixed planting reminiscent of a traditional formal border includes marigolds and classic red salvia (Salvia splendens) with taller layers of colourful zinnias and stately, white-flowered Nicotiana.

“I would have had more zinnias this year if it hadn’t been for the cold weather we experienced in spring,” says Robert, who is an avid gardener. “I transplanted 350 seedlings in the spring and kept them in our gazebo, but I only had one heater running and 80 per cent of them died.” Robert started new plants from seed and filled one entire bed with zinnias which quickly grew thigh-high once warmer temperatures arrived.

Read
2:00 AM CDT

Frustration on menu as St. James construction drags on

Kelly-Anne Riess 4 minute read Preview

Frustration on menu as St. James construction drags on

Kelly-Anne Riess 4 minute read Updated: Yesterday at 11:18 AM CDT

Nearly four months of construction outside the front door of a longtime Portage Avenue restaurant has driven away customers and left its owner struggling to cover operating expenses.

Read
Updated: Yesterday at 11:18 AM CDT

WAG-Qaumajuq names first Indigenous director, CEO

Jen Zoratti 4 minute read Preview

WAG-Qaumajuq names first Indigenous director, CEO

Jen Zoratti 4 minute read Thursday, Oct. 22, 2026

John Mahli Lawa’ Hampton has been selected to take the helm of Canada’s oldest civic art gallery, WAG-Qaumajuq announced Thursday.

Read
Thursday, Oct. 22, 2026