Hydro embarks on $7-billion overhaul of two main transmission lines Undertaking will ensure ‘reliable’ power grid for future, utility says

Manitoba Hydro has launched a historic and long overdue overhaul of its two main transmission lines that will cost at least $7 billion and require up to 15 years of electricity rate hikes, the Free Press has learned.

Read this article for free:


or

Already have an account? Log in here »

To continue reading, please subscribe:

Subscribe and receive a limited-edition Free Press branded hat or tote.

Digital Subscription

One year of digital access for only $205*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.

To continue reading, please subscribe:

Add Free Press access to your Brandon Sun subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Start now

*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

Hey there, time traveller!
This article was published 15/07/2025 (425 days ago), so information in it may no longer be current.

Manitoba Hydro has launched a historic and long overdue overhaul of its two main transmission lines that will cost at least $7 billion and require up to 15 years of electricity rate hikes, the Free Press has learned.

The HVDC (high-voltage direct current) Reliability Project involves the replacement of the converter stations and other equipment at both ends of Bipoles I and II, the two main transmission lines that each run nearly 1,000 kilometres from northern Manitoba through the Interlake to Winnipeg. The two lines carry more than 70 per cent of Hydro’s total generated electricity.

WAYNE GLOWACKI / FREE PRESS FILES
                                Manitoba Hydro has launched a historic and long overdue overhaul of its two main transmission lines that will cost at least $7 billion.

WAYNE GLOWACKI / FREE PRESS FILES

Manitoba Hydro has launched a historic and long overdue overhaul of its two main transmission lines that will cost at least $7 billion.

Hydro has estimated the project will cost at least $7 billion, although because it is still at a very early stage, officials at the utility concede the final price tag will be higher.

A Hydro spokesman confirmed the utility has started a procurement process that will establish a precise cost to replace the converter stations and is conducting a search for contractors to oversee the work. A more accurate estimate of the total cost will not be available until “the full scope of work” is identified, the spokesman said.

Even at $7 billion, this would be the most expensive capital project undertaken by the Crown corporation, exceeding the investments made in any single generating station. It’s significantly more than the cost of Bipole III, the politically controversial transmission line that runs from the north along the west side of Lake Manitoba. Bipole III was completed in 2018 at a cost of just over $5 billion.

Hydro’s 2026-28 rate application, which has been filed with the Public Utilities Board, said the project would take more than a decade to complete and based on Hydro’s latest calculations, require 15 years of annual rate increases of 3.5 per cent.

Although electricity rate increases are politically unpopular, Hydro will argue before the PUB that the viability of the transmission system is at stake if the work is not done.

“This is not just about meeting new energy needs in the future,” said Ben Graham, chairman of the Hydro board of directors. “It’s about ensuring a reliable grid now so that Manitobans will have the power they need when they need it.”

MIKE DEAL / FREE PRESS FILES
                                Manitoba Finance Minister Adrien Sala, the minister responsible for Hydro, says the NDP government approved the HVDC project as part of its process of reviewing the utility’s 2025-26 budget.

MIKE DEAL / FREE PRESS FILES

Manitoba Finance Minister Adrien Sala, the minister responsible for Hydro, says the NDP government approved the HVDC project as part of its process of reviewing the utility’s 2025-26 budget.

Finance Minister Adrien Sala, the minister responsible for Hydro, said the NDP government approved the HVDC project as part of its process of reviewing the utility’s 2025-26 budget. He said that despite urgings from Hydro, the previous Tory government ignored the state of the transmission line converters and deferred a formal decision about starting the HVDC project.

“We know for many years, the former government failed to make necessary investments to ensure continued reliability at Hydro, and also ensure that we would have the energy we needed to support Manitobans and our businesses,” Sala said. “So, I think we’re making sure that we keep that all important balance between preserving affordability while ensuring Manitobans have access to the energy they need to power their homes and their businesses.”

“For many years, the former government failed to make necessary investments to ensure continued reliability at Hydro.”–Finance Minister Adrien Sala

Peggy Barker, board member with the Manitoba branch of the Consumers’ Association of Canada, which monitors Hydro rate applications to the PUB, said she’s concerned about the size and speed of the project given Hydro’s poor performance in forecasting the cost of capital projects.

“For over 10 years, the Public Utilities Board and independent experts have said that Manitoba Hydro’s process for deciding on the pacing and prioritization of asset management was not mature or adequate,” the association’s statement said. “While Hydro has made modest progress in recent years, there is still an absence of a mature, standardized methodology for ranking investments based on asset risk, customer value, and cost-effectiveness.”

MARC GALLANT / FREE PRESS FILES
                                Manitoba is known throughout the energy world for technology that has allowed electricity to be transmitted via high-voltage direct current lines over extremely long distances.

MARC GALLANT / FREE PRESS FILES

Manitoba is known throughout the energy world for technology that has allowed electricity to be transmitted via high-voltage direct current lines over extremely long distances.

Bipole I went into operation in 1971 and underwent a major upgrade in 1993. Bipole II was fully completed in 1985. Currently, the converter stations that are essential for the transmission of power to the south are well past their life expectancy.

Given the long distances the electricity must travel, converter stations are needed to convert alternating current (AC) that comes from the generating stations to direct current (DC) for transmission to reduce the amount of electricity lost during transmission. When the electricity reaches the other end of the transmission line, it is converted back to AC.

In most instances, the converter stations are more expensive than the cost of erecting hundreds of kilometres of transmission lines.

According to Hydro, the converter equipment normally has a life span of 35 years. Hydro currently estimates the earliest it could acquire and install new converters and connectors is between 2032 and 2037. By that time, the Bipole I converters will be 44 years old and its control mechanisms will be 65 years old, while Bipole II converters and controls will be more than 50 years old.

Although the cost estimate and electricity rate hikes could be a source of political controversy, the need for the refurbishment project should not be a cause for much disagreement between the NDP government and opposition parties.

The distance between northern generating stations and the southern region of the province, where most of the electricity is consumed, has always been a major source of concern for Hydro and the government of the day.

MIKE DEAL / FREE PRESS FILES
                                Former Tory premier Brian Pallister called Bipole III the worst political scandal in the province’s history and spent $1 million on an in-depth review of the project.

MIKE DEAL / FREE PRESS FILES

Former Tory premier Brian Pallister called Bipole III the worst political scandal in the province’s history and spent $1 million on an in-depth review of the project.

In 1996, a huge wind storm damaged both Bipole I and II and nearly resulted in a blackout of Winnipeg. Hydro was forced to import electricity from Minnesota while both transmission lines were being repaired.

Ultimately, that event became the motivation for the construction of Bipole III. Again, the need for the project was never really questioned; the cost and management of it by the then-NDP government of Gary Doer sparked years of political conflict.

The final cost was nearly three times the initial estimate and the project was afflicted by numerous delays and mismanagement.

Former Tory premier Brian Pallister called Bipole III the worst political scandal in the province’s history, and spent $1 million to have former Saskatchewan premier Brad Wall, a Tory, conduct an in-depth review. The Wall review did not reveal new details about the project.

The big question facing Hydro, and successive provincial governments of both political stripes, is why the HVDC project was delayed.

By all accounts, Hydro has been planning for decades to replace essential equipment at both ends of the transmission lines. However, documents available at the PUB and legislative committee meetings show it was not discussed in detail until about 2016. An engineering report released by Hydro in 2019 fully explored the danger of pushing the equipment too far beyond its normal life span.

The 2026-28 general rate application, now before the PUB, is the most detailed description yet of the need for, and cost of, replacing transmission converters and connectors.

Manitoba is known throughout the energy world for technology that has allowed electricity to be transmitted via high-voltage direct current lines over extremely long distances. Bipole I (895 kilometres) and II (937 kilometres) run from the northern Radisson and Henday converter stations near Gillam, down to the Dorsey converter station just northwest of Winnipeg.

Bipole III is much longer at 1,400 kilometres, starting at the Keewatinohk converter station near Gillam and ending at the Riel converter station east of Winnipeg.

However, in its most recent submission, Hydro noted that Manitoba currently operates the oldest HVDC transmission system in the world.

dan.lett@freepress.mb.ca

Dan Lett

Dan Lett
Columnist

Dan Lett is a columnist for the Free Press, providing opinion and commentary on politics in Winnipeg and beyond. Born and raised in Toronto, Dan joined the Free Press in 1986.  Read more about Dan.

Dan’s columns are built on facts and reactions, but offer his personal views through arguments and analysis. The Free Press’ editing team reviews Dan’s columns before they are posted online or published in print — part of the our tradition, since 1872, of producing reliable independent journalism. Read more about Free Press’s history and mandate, and learn how our newsroom operates.

Our newsroom depends on a growing audience of readers to power our journalism. If you are not a paid reader, please consider becoming a subscriber.

Our newsroom depends on its audience of readers to power our journalism. Thank you for your support.

Report Error Submit a Tip

More Stories

Citizen reports help highlight connectivity issues across southwest Manitoba

Nicole Buffie 5 minute read Preview

Citizen reports help highlight connectivity issues across southwest Manitoba

Nicole Buffie 5 minute read Updated: 10:43 AM CDT

A southwestern Manitoba man has created a map to document cell service blackout spots in an effort to push for better access in rural areas.

Mark Custance compiled more than 300 citizen reports over the last few months to document where service in southwest Manitoba is strong, spotty or doesn’t exist at all.

“I’ve heard people complain and say, ‘cell service sucks’ or ‘this is not working.’ But what does the data actually say?” Custance said from his office in Melita, where he has installed a cell-service booster to maintain connectivity with the rest of the world.

Analyzing where service is good and poor, he cross-references it with the location of cellphone towers across the region.

Read
Updated: 10:43 AM CDT

Education minister’s reasons for revoking teacher’s licence ‘not good enough,’ judge decides

Maggie Macintosh 6 minute read Preview

Education minister’s reasons for revoking teacher’s licence ‘not good enough,’ judge decides

Maggie Macintosh 6 minute read Updated: Yesterday at 9:14 AM CDT

A Manitoba judge has rejected the education minister’s decision to end a teacher’s career because he repeatedly messaged with a 13-year-old girl on social media.

Read
Updated: Yesterday at 9:14 AM CDT

Nifty neighbours also jonesing for geniality

Maureen Scurfield 4 minute read 2:01 AM CDT

DEAR MISS LONELYHEARTS: Recently, a new couple with no children moved onto our cul de sac, and everybody is taking notice! This attractive pair with no kids both drive amazing cars, work from home and leave their garage doors up a lot. Everybody on the street walks by to sneak a peek into the big garage at just about any time of day.

Lately, the man’s been out on his front lawn in a muscle shirt in the late afternoon, planting shrubs and putting up stylish fall-themed ornaments. At night they often leave the living-room curtains open. That makes for convenient viewing for curious neighbours like us!

A few days ago, my wife invited the new couple over for a barbecue and swim in our pool. They are really nice people, but mentioned that other people nearby have been pretty stand-offish. They wonder why. Should I tell them it’s probably just jealousy over their beautiful vehicles and enviable lifestyle, or should I just shut up?

—Wanting to Help, Sage Creek

Is Trump about to poke Quebec’s political beehive?

Peter McKenna 6 minute read Preview

Is Trump about to poke Quebec’s political beehive?

Peter McKenna 6 minute read 2:00 AM CDT

When was the last time that a U.S. president seriously stirred the hornet’s nest of Quebec politics?

My best recollection is former U.S. president Bill Clinton. During the 1994 Quebec referendum campaign, Clinton made clear that the U.S. wholly endorsed a united and strong federal Canada — as opposed to a dismembered one. He went on to add that an independent Quebec would have no guarantee of joining the North American Free Trade Agreement as a full-fledged member.

Today, we see U.S. President Donald Trump inserting himself — unwittingly or wittingly — into the electoral and sovereignty politics of Quebec. It’s pretty clear that the resurgent Coalition Avenir Québec government is trying to make the Oct. 5 provincial election about anything other than its own governmental record and more about Trump’s economic coercion against Canada. Of course, the Parti Québécois, the odds-on-favourite, wants to make the electoral contest a referendum on the CAQ and its party leader, Christine Fréchette.

But what if Trump really wanted to make his presence felt in Quebec’s political life? How much influence could he have on shaping political outcomes in Quebec? How much of an “X factor” could he be?

Read
2:00 AM CDT

City rapped for taking five days to remove animal carcass

Morgan Modjeski 2 minute read Thursday, Sep. 10, 2026

A Winnipeg resident said she’s upset it took the city five days to retrieve a dead fawn from her yard after she reported it to 311.

Amy Gelhorn said she and her family noticed the animal carcass in her garden on Saturday. She called 311 and was told it would be picked up after the long weekend.

“It was removed this afternoon,” the north River Heights resident said Thursday. “So it took six days to remove it and we had to basically phone every day.”

She said neighbours on both sides of her house told her they saw the animal acting strangely on Friday and reported their concerns to 311. It’s believed the animal died overnight. As the days dragged on, the body continued to rot.

Retired sportscaster Scott Oake determined as fundraising for women's addictions treatment facility enters home stretch

Melissa Martin 4 minute read Preview

Retired sportscaster Scott Oake determined as fundraising for women's addictions treatment facility enters home stretch

Melissa Martin 4 minute read Thursday, Sep. 10, 2026

For now, the patch of land just east of the Victoria Hospital doesn’t look like much: just a field of rocks, mounded dirt, and concrete piles driven into the earth. Yet when Scott Oake looks over the site, he can already imagine how it will look in just over a year’s time, when the new Anne Oake Family Recovery Centre is expected to open.

It’s easier to picture this time around. In 2020, when the recently-retired CBC sportscaster and his late wife, Anne, were building their first labour of intermingled grief and love, the Bruce Oake Recovery Centre for men, it was hard for him to wrap his mind around how a raw construction site could transform into a welcoming addictions treatment facility.

When that centre opened in 2021, Oake found it looked “almost identical” to the architect’s renderings. So it’s easy to hope the Anne Oake Centre will be the same. It will be the first facility of its kind, its founders believe, not only in Canada but in North America: a place where 50 to 70 women can pursue sobriety while staying with their children.

“At Bruce Oake there’s a culture of love, and most of all a culture of hope,” Oake said, speaking at the site Thursday after a media conference to announce the final push of the centre’s fundraising campaign. “I can feel it every time I walk into that building. And I know it will be the same here.”

Read
Thursday, Sep. 10, 2026