Ambitious Centre Block renovation project nearly ready to enter the rebuilding phase

Advertisement

Advertise with us

OTTAWA - The major restoration of Parliament's Centre Block is nearly ready to enter the rebuilding phase after six years of demolition, primary excavation and abatement.

Read this article for free:


or

Already have an account? Log in here »

To continue reading, please subscribe:

Subscribe and receive a limited-edition Free Press branded hat or tote.

Digital Subscription

One year of digital access for only $205*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.

To continue reading, please subscribe:

Add Free Press access to your Brandon Sun subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Start now

*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

Hey there, time traveller!
This article was published 14/11/2024 (695 days ago), so information in it may no longer be current.

OTTAWA – The major restoration of Parliament’s Centre Block is nearly ready to enter the rebuilding phase after six years of demolition, primary excavation and abatement.

The renovation is estimated to cost between $4.5 billion and $5 billion. Siavash Mohajer, senior construction director with Public Service and Procurement Canada, said that despite inflation the budget estimate remains on track, but rising costs have applied pressure to the project.

The overhaul removed tonnes of asbestos and is bringing the building up to modern day standards and safety codes including for technical capabilities. It’s also adding a brand new visitor centre which will serve as the main public entrance to parliament with access to all three buildings on the hill.

A photographer takes photos of the House of Commons during a tour of work being completed to Centre Block, Thursday, Nov. 14, 2024 in Ottawa. THE CANADIAN PRESS/Adrian Wyld
A photographer takes photos of the House of Commons during a tour of work being completed to Centre Block, Thursday, Nov. 14, 2024 in Ottawa. THE CANADIAN PRESS/Adrian Wyld

The new visitor centre will include an expanded security screening area, which planners say will allow greater visitor access. Currently, the annual tour group capacity is around 350,000 people, but the expanded screening area is expected to double that amount.

The renovation began in 2018 and is expected to be complete in either 2030 or 2031. The building isn’t expected to reopen until 2032, allowing for facility testing to ensure operations are smooth.

The conceptual design for the appearance of the new visitor centre is expected to be finalized in fall 2025.

With the new visitor centre being built underneath the existing structure and around the foundation of Peace Tower, workers are currently installing hundreds of steel supports to hold up the building while the renovations are completed.

More precise excavation has begun to carve out rock and earth for this visitor centre, but it is expected to be a slow process. Dynamite was used to blast away rock during the primary excavation, but that is no longer possible at this point.

Seismic shock absorbers are also being installed to match modern building codes. This work would earthquake proof Centre Block for an up to 6.5 magnitude tremor.

On top of engineering complexities, the renovation is a massive heritage undertaking. All heritage items that can be removed from Centre Block have been for storage and restoration work if needed.

This means areas like the House of Commons and senate chambers have been stripped to their bare bones so restoration work can take place.

“When it does return, all of the heritage elements will come back and it will look mostly the same,” Louise Cowley, director of long term vision and plan with the Senate said.

It was deemed that the stained glass windows in the senate chamber held no heritage value, so Cowley said a juried competition will be launched in the future to find Canadian artists to design new ones.

The revised Senate chamber will also be set up so proceedings can be publicly broadcast.

Making the buildings fully accessible for mobility devices like wheelchairs does mean public seating in the galleries be reduced. Before the renovation began the House of Commons could accommodate around 580 people, and project director Darrell de Grandmont estimates there will be 100 fewer seats once it reopens.

Seating for MPs in the House of Commons will also need to change in the future. Under heritage rules, the chamber cannot be made bigger but the amount of MPs will increase by the time it reopens.

De Grandmont says some considerations include doing away with assigned seating for parliamentarians or getting rid of desks in favour of benches, as is seen in British parliament.

Some heritage elements are being redone entirely, such as stone carvings on the exterior of the building that are too weather-worn to be restored.

Sculptor Danny Barber showed off a stone bison carving that will be placed on the west side of the building to replace a damaged original.

Barber worked on the carving over the summer using hand tools and said he takes great pride in bringing out the fine details from the original, such as the curls in the animal’s mane and sheaves of wheat flanking the beast.

“It’s easy to kind of get overwhelmed, so you have to break it down into the small pieces so you really have to pull back from the overall design,” he said.

“I’m very proud to be working on this project, it isn’t the sort of thing you get on our workbenches very often.”

Through the deconstruction process, the project team uncovered some previously hidden design elements, like intricately stencilled patterns painted on the walls of the speaker’s dining room.

The decision was made to incorporate these stencils into the renovation, among other changes to capture the original building character.

“There are areas that had been carpeted over floor, and that floor was the original floor back in the day. It’s been really this uncovering of a lot of the history of the building overtime, it’s been actually remarkable,” de Grandmont said.

Once work is complete the new Centre Block is expected to be a fully accessible parliament with a new IT backbone built in behind the familiar heritage facade.

Mohajer said that the end goal is to have it be a modern building with new additions that can last for the next 100 years.

This report by The Canadian Press was first published Nov. 14, 2024

Report Error Submit a Tip

More Stories

Bit of creepy consultation could go a long way

Maureen Scurfield 5 minute read Yesterday at 2:01 AM CDT

DEAR MISS LONELYHEARTS: Halloween has always been my favourite time of year. I do my house up with lots of spooky lighting and characters on the lawn with eerie sounds booming out.

But last year I got seriously hassled by some people in the neighbourhood who thought it was too creepy. How do I get them on board this year? I don’t want to fight with them again.

— Want to Be Good Neighbour, River Heights

Dear Good Neighbour: Go to your close neighbours and explain what you want to do with your yard for Halloween this year, and also provide them with a firm time by which the celebrating will wrap up and things can quiet down.

Ambitious Centre Block renovation project nearly ready to enter the rebuilding phase

David Baxter, The Canadian Press 5 minute read Preview

Ambitious Centre Block renovation project nearly ready to enter the rebuilding phase

David Baxter, The Canadian Press 5 minute read Thursday, Nov. 14, 2024

OTTAWA - The major restoration of Parliament's Centre Block is nearly ready to enter the rebuilding phase after six years of demolition, primary excavation and abatement.

The renovation is estimated to cost between $4.5 billion and $5 billion. Siavash Mohajer, senior construction director with Public Service and Procurement Canada, said that despite inflation the budget estimate remains on track, but rising costs have applied pressure to the project.

The overhaul removed tonnes of asbestos and is bringing the building up to modern day standards and safety codes including for technical capabilities. It's also adding a brand new visitor centre which will serve as the main public entrance to parliament with access to all three buildings on the hill.

The new visitor centre will include an expanded security screening area, which planners say will allow greater visitor access. Currently, the annual tour group capacity is around 350,000 people, but the expanded screening area is expected to double that amount.

Read
Thursday, Nov. 14, 2024

Police on scene at Fairmont hotel construction site

1 minute read Updated: Yesterday at 12:19 AM CDT

At least three police cars were present at the under-construction Fairmont Winnipeg Thursday evening.

The nature of the response was unclear, but officers were guiding traffic outside of the construction zone at 2 Lombard Place while the response was underway. At 6:50 p.m., traffic was flowing normally.

Security on site provided no information on the response, but an individual working behind site fencing told the Free Press there’d be no comment from anyone on site as to why police were on scene at this time.

An SUV with a Government of Manitoba logo on its side was also present alongside personnel from Manitoba Workplace Safety and Health. However, it’s unknown if it’s connected to the police response.

Person killed in workplace accident at Fairmont construction site

Morgan Modjeski 3 minute read Preview

Person killed in workplace accident at Fairmont construction site

Morgan Modjeski 3 minute read Updated: Yesterday at 8:30 PM CDT

Emergency responders were on scene and Manitoba Workplace Safety and Health is investigating after a worker died following an incident at a Winnipeg construction site Thursday.

Little information about the worker killed was provided, but the fatal incident happened at the Fairmont Winnipeg, located at 2 Lombard Place, with police responding around 5 p.m.

The hotel is currently closed and is an active construction site. The person killed has not been identified by name.

Information from a provincial spokesperson said the deceased was working for Kepsco Construction when they were fatally injured after a “portion of an overhead canopy collapsed during asbestos abatement work.”

Read
Updated: Yesterday at 8:30 PM CDT

Puzzles Palace

1 minute read Monday, Jul. 27, 2026

To solve our puzzles, please subscribe with this special offer: |

Final hurdles are moving on in your mind and life

Maureen Scurfield 3 minute read 2:01 AM CDT

DEAR MISS LONELYHEARTS: I just ran into my former husband with his new woman. It was a shock. She looked nothing like me — not nearly as good. In fact, she’s the opposite of me — red-haired, freckled, tall and skinny like a rake. I’m short, dark, with golden skin from my Italian background. That was what my husband used to say he loved in a woman.

Does that mean he lied — that he really didn’t like my looks and secretly longed for the opposite? That seems crazy to me. But I should mention that in our last miserable years together he didn’t even want to hold me in his arms and look at me. He sometimes slept at his office (or so he said) because he was “too tired to drive home.”

He could have been elsewhere — like in some other woman’s home — because he always used his cellphone to call me, not his office line.

How can I forget about the man I loved so much and finally move on?