Amid growing public backlash to the rapid buildout of data centers across Texas, Gov. Greg Abbott on Monday announced a moratorium on the approval of data centers until regulatory agencies can audit proposed data centers seeking connection to the state’s electric grid.

Read this article for free:

or

Already have an account? Log in here »

To continue reading, please subscribe:

Subscribe and receive a limited-edition Free Press branded hat or tote.

Digital Subscription

One year of digital access for only $205*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.

To continue reading, please subscribe:

Add Free Press access to your Brandon Sun subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Start now

*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

Amid growing public backlash to the rapid buildout of data centers across Texas, Gov. Greg Abbott on Monday announced a moratorium on the approval of data centers until regulatory agencies can audit proposed data centers seeking connection to the state’s electric grid.

It is unclear how long the audit will take, but the effort is Abbott’s strongest effort yet to slow the development of these data centers statewide and underscores how little information members of the public, including state leaders, know about the facilities.

Abbott is asking the Public Utility Commission of Texas and the Electric Reliability Council of Texas to ensure data center developers provide information on tax breaks they will receive; power use and generation; water use and cooling operations; efforts to reduce impacts on local communities; and ownership of the facility. Any projects that fail Abbott’s ordered “comprehensive verification and audit” should be denied connection to the grid, the governor said.

“Our top priority is to protect Texans’ safety and quality of life,” Abbott wrote in a statement. “Any project that fails to comply with the requirements set forth by the PUCT and ERCOT, and by state law, must be denied connection to the Texas grid. Simply put, Texans must come first.”

Abbott’s letter to the PUCT and ERCOT directs them to conduct the audit on all data centers advancing through ERCOT’s interconnection queue, or the line for energy intensive projects seeking connection to the electric grid. ERCOT is currently tracking more than 1,800 projects in the queue, representing over 474 gigawatts of electricity, or more than five times the grid’s record for peak demand, according to ERCOT. Approximately 90% of the new power requests are data centers, Abbott said.

ERCOT and the PUCT are already conducting a review of some of the projects in the queue through a process known as “batch zero.” It is unclear if Abbott wants agencies to audit those projects or all those currently in the queue. Following Abbott’s directive, ERCOT said Monday they are putting the batch zero review on pause.

There is no state or federal government database of the facilities, but the Texas Tribune has identified at least 335 data centers operating in Texas. The state is currently the second largest market for the facilities in the country, behind Virginia, and is poised to take the top spot. The Tribune has identified at least 248 planned data centers coming to the state, although hundreds more in lesser development phases have lined up in the power queue.

While Abbott’s directive pauses the approval of new data centers seeking connection to the ERCOT grid, some data centers are building on-site power generation that allows them to bypass traditional connection to the grid. The ERCOT region also does not include the entirety of the state, like El Paso, which has seen the development of several large data centers.

The Data Center Coalition, a trade group that represents some of the nation’s largest tech companies, said it was hopeful Abbott’s directive could separate responsible developers from irresponsible ones and urged regulators to quickly conduct the audits.

“Done correctly, this review can showcase the good actors in the data center industry rather than delaying them unnecessarily, ensuring Texas will continue to be the national leader in economic development,” the organization’s spokesman Dan Diorio wrote in a statement Monday.

Lack of transparency

Lawmakers have spent much of this year seeking clarity about the facilities’ electricity use, water use and access to tax incentives as the Legislature considers tighter regulation of the industry.

Abbott cited the failure of some data centers to comply with a recent PUCT’s survey measuring water and power usage as the reason the audit was needed because it hinders the agencies’ ability to make informed decisions.

Developed by the PUCT in collaboration with the Texas Water Development Board, the survey collects information about a data center’s water consumption, cooling systems, water sources, electricity demand and whether facilities are connected to the state’s electric grid or have their own on-site power source such as a gas-fired power plant. The responses are meant to inform long-term state water planning.

State law requires the PUCT to share the data with the water development board and state environmental regulators and to submit a report to the governor and the Legislative Budget Board by the end of the year.

Rep. Brad Buckley, R-Salado, a member of the House Natural Resources Committee called survey participation “pretty pathetic” during a June hearing. Of the 377 companies PUCT staff said it notified when the survey was launched, 28 submitted responses.

Also in June, Abbott directed the PUCT and ERCOT to require data centers fully fund the costs of electric infrastructure needed to serve them and take other measures to reduce electricity costs to residents.

On July 17, PUCT Chair Thomas Gleeson responded to Abbott with his own letter outlining efforts the agencies have already taken and calling on the Legislature to grant them more authority to regulate the industry.

The PUCT did not respond to questions about the scope of the audit, saying the agency would work with ERCOT to ensure Abbott’s new directives are carried out.

Abbott’s proposal may disrupt ERCOT’s ongoing rework of its approval process for projects in the interconnection queue, requiring large-load projects to provide more detailed information before they can advance. The new rules for the first set of projects under consideration, known as “batch zero,” were approved by the PUCT in June. The agencies are currently working to develop a more permanent set of rules for projects still in the queue.

An ERCOT spokesperson said the grid manager is reviewing Abbott’s order and will postpone the batch zero transmission planning study that is currently underway.

Calls for a full moratorium

City and county governments in the state have tried to slow data center development amid grassroots resistance to the facilities’ construction. Hood County rejected two attempts to pass a countywide moratorium in February after state Sen. Paul Bettencourt, R-Houston, warned the commissioners court it lacked the legal authority to do so. In May, Hill County approved the state’s first moratorium on the development of data centers but rescinded the measure a month later after a developer sued for $100 million in damages. And in June, San Marcos became the first Texas city to issue such a moratorium.

Nationally, New York Gov. Kathy Hochul, a Democrat, faced criticism from President Donald Trump after she last month issued a year-long pause on the construction of the largest data centers.

Opponents of the data center industry say Abbott’s Monday directive to regulators comes up short of a true moratorium.

Texas Department of Agriculture Commissioner Sid Miller called Abbott’s directive vague and said it was not a substitute for legislative action, although he applauded the additional scrutiny.

“Without legislative action, this directive is all hat and no cattle — empty political rhetoric wrapped in meaningless fluff,” Miller wrote. “Texans need laws with teeth, not another press release designed to make it look like something is being done while hyperscale projects continue moving forward.”

Miller, along with many other opponents of data center development, has been calling on Abbott to order a special session that would allow legislators to pass laws regulating the industry.

“AI has real promise, but it shouldn’t come at the cost of our water, our air, and our neighborhoods,” said Luke Metzger, executive director of Environment Texas, in a written statement about the need for a data center-focused special session. “Now that the state is asking the right questions, it needs to use the answers to develop safeguards that protect Texans.”

State Rep. Gina Hinojosa, an Austin Democrat running against Abbott, said his directives do not go far enough.

“So nice to see another strongly worded letter from Abbott after he proudly made Texas the wild west of data centers,” Hinojosa wrote in a statement. “Abbott’s call for a ‘pause’ could be for one day – and no one buys it. He’s taken millions from data center CEOs while giving Texans lip service to non-existent restrictions.”

___

Alejandra Martinez contributed to this report.

___

This story was originally published by The Texas Tribune and distributed through a partnership with The Associated Press.

Report Error Submit a Tip

More Stories

Federal government to build $267-M emergency research lab in Winnipeg

Chris Kitching 6 minute read Preview

Federal government to build $267-M emergency research lab in Winnipeg

Chris Kitching 6 minute read Updated: Yesterday at 4:42 PM CDT

The federal government says it will build a $267-million medical countermeasures laboratory in Winnipeg with the goal of preparing Canada for future pandemics or outbreaks.

Expected to open in 2033, the national site will help the country develop vaccines, therapeutics and diagnostic tools, Winnipeg Liberal MP Terry Duguid said.

“This is a big deal for our city and for our province, a big deal for life sciences in Canada,” he told reporters Wednesday. “This facility is going to help protect the nation and help protect the world.”

Ottawa said the site — to be located next to the National Microbiology Laboratory’s Canadian Science Centre for Human and Animal Health on Arlington Street, just north of William Avenue — draws on lessons learned during the COVID-19 pandemic.

Read
Updated: Yesterday at 4:42 PM CDT

New sci-fi/fantasy bookstore a welcome addition

Ben Sigurdson 5 minute read Preview

New sci-fi/fantasy bookstore a welcome addition

Ben Sigurdson 5 minute read 4:46 PM CDT

A new chapter has begun in Winnipeg’s literary landscape with the opening of science fiction and fantasy bookstore Other Places Books.

Located at 436 Graham Ave., the queer-owned and operated shop is the latest in a host of genre bookstores to have opened in the city over the last few years. In addition to longtime mainstay Whodunit? Mystery Bookstore (163 Lilac St.), the local scene now also features a horror bookstore (Raven’s End Books, which opened at 1859 Portage Ave. in 2024) and a shop focused on romance (Bound to Please, which opened at 995 McPhillips St. earlier this year).

The 900 titles currently in stock at Other Places, which opened Tuesday, span a range of sci-fi and fantasy sub-genres, with a particular focus on queer writers and storylines. The bookstore is the brainchild of Didi Chanoch, who moved to Winnipeg from Israel in 2025 after the Canadian federal government began offering work permits to those in Israel and Palestine looking to leave the area due to the conflict.

Winnipeg ended up on Chanoch’s radar in large part due to a more reasonable cost of living than other Canadian cities.

Read
4:46 PM CDT

Puzzles Palace

1 minute read Monday, Jul. 27, 2026

To solve our puzzles, please subscribe with this special offer: |

Drunk driver who killed cycling couple, orphaned their infant daughter, sentenced to eight years

Dean Pritchard 4 minute read Preview

Drunk driver who killed cycling couple, orphaned their infant daughter, sentenced to eight years

Dean Pritchard 4 minute read Tuesday, Aug. 4, 2026

A Winnipeg man responsible for a drunk-driving crash that killed two cyclists last summer and left their infant child an orphan has been sentenced to eight years in prison.

Kuldeep Singh Gill was arrested Sept. 13 after fleeing from a high-speed collision on Kenaston Boulevard that killed 31-year-old Egor Popov and his 25-year-old common-law partner Kerry Ashley Bonner.

Gill, 46, pleaded guilty earlier this year to two counts of impaired driving causing death and two counts of failing to stop at the scene of a collision.

Gill, who has a prior conviction for impaired driving, made a conscious decision to drive drunk, knowing it made him a danger on the road, provincial court Judge David Ireland said at a sentencing hearing Tuesday.

Read
Tuesday, Aug. 4, 2026

U of M researchers studying ‘digital legacy planning’ before death

Maggie Macintosh 6 minute read Preview

U of M researchers studying ‘digital legacy planning’ before death

Maggie Macintosh 6 minute read Yesterday at 6:10 PM CDT

A team of researchers at the University of Manitoba wants adults to take the cloud they leave behind into special consideration when they envision heaven and their afterlife.

Read
Yesterday at 6:10 PM CDT

Letters, Aug. 6

7 minute read Updated: 12:23 PM CDT

As the former senior vice-president and chief financial officer for Manitoba Hydro, I cringe whenever I see negative references in the media and elsewhere regarding Manitoba Hydro’s long-term debt.