New Brunswick data centre debate highlights cross-country tension over AI facilities

Advertisement

Advertise with us

FREDERICTON - Chris Watson says he was very concerned when he reviewed a New Brunswick business development agency's recent correspondence about data centres.

Read this article for free:


By clicking the button above, an account will be created and you will begin to receive some of our recommended newsletters. You may opt out of any newsletter by visiting your Email and Communication Preferences page or by clicking "unsubscribe" at the bottom of any email.

or

Already have an account? Log in here »

To continue reading, please subscribe:

Digital Subscription

One year of digital access for only $1.44 a week*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*Billed as $5.77 plus GST every four weeks. After 52 weeks, price increases to the regular rate of $19.95 plus GST every four weeks. Offer available to new and qualified returning subscribers only. Cancel any time.

To continue reading, please subscribe:

Add Free Press access to your Brandon Sun subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Start now

*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

FREDERICTON – Chris Watson says he was very concerned when he reviewed a New Brunswick business development agency’s recent correspondence about data centres.

Over the past year, he has been at the forefront of citizen-led opposition to a major data centre project in his neighbourhood in Saint John, N.B.

But when he reviewed the correspondence, released through right-to-information legislation by Opportunities New Brunswick, he discovered the existence of another proposal from a company trying to bring one of the energy-hungry projects to his area.

A group of allied New Brunswick residents opposing what could be the first hyperscale data centre in Atlantic Canada say they’ve uncovered a proposal for a second, smaller one nearby. People in opposition to AI data centres demonstrate outside the council chambers at city hall in Hamilton, Wednesday, July 15, 2026. THE CANADIAN PRESS/Nick Iwanyshyn
A group of allied New Brunswick residents opposing what could be the first hyperscale data centre in Atlantic Canada say they’ve uncovered a proposal for a second, smaller one nearby. People in opposition to AI data centres demonstrate outside the council chambers at city hall in Hamilton, Wednesday, July 15, 2026. THE CANADIAN PRESS/Nick Iwanyshyn

“It’s not surprising, but it’s just deeply disappointing,” he said in a recent interview with The Canadian Press.

Watson said the correspondence shows how New Brunswick is entertaining data centre proposals without sharing important information with the people who will be most affected. 

He also said it shows how the provincial government is scrambling to review projects without adequate rules or guidelines to ensure it can protect both citizens and the environment.

NB Power, the province’s Crown-owned electric utility, confirmed there are 10 applications from data centre projects that would need up to 900 megawatts of power. 

But the utility is declining to identify all of the projects on this list, saying that the applications are confidential. A spokesperson would not confirm if the publicly known projects are on the list.

The Liberal provincial government sees the plants as a potential opportunity to generate economic growth through tax revenue, private sector buy-in and job creation.

The debate playing out in New Brunswick highlights the challenges facing provincial and municipal governments as they face a surge in applications for data centres. 

The facilities can range in size from a micro data centre about the size of a refrigerator to a hyperscale campus that consumes a level of power comparable to a small city.

The New Brunswick government is currently working on a policy framework for data centre development that it recently sought public feedback on.

“Data centre development could be an opportunity for New Brunswick to generate economic growth through tax revenue, private sector investment, construction and permanent job creation, and potential offshoot economic and community benefits,” the provincial government said on its feedback page.

Watson, who is part of a grassroots community group called Save Lorneville, says the government should impose a moratorium on new data centre projects until it has stronger policies in place to protect residents, businesses and the environment.

Among the publicly known proposed data centres in New Brunswick, none have acquired final approval.

A 400-megawatt data centre is at the heart of a $2 billion artificial intelligence hub proposed through a joint venture by Beacon Data Centers of Alberta and U.S. firm VoltaGrid.

The Beacon Data Centers project will get about half its power from the grid and the rest from an on-site power plant. It’s currently under regulatory review. 

Billed as Atlantic Canada’s first hyperscale artificial intelligence facility, the project sparked intense backlash from some residents who lived near the industrial park where it’s set to be built, including Watson and his group.

Just this month, Fredericton-based Faster Than Light introduced its plan for a $2.7 billion, 375-megawatt data centre publicly for the first time. 

And then there is the proposal from U.S. firm Cross River Infrastructure Partners that was discovered by Watson and his neighbourhood advocacy group. The proposal is located in the same Spruce Lake Industrial Park as the Beacon Data Centers project.

Cross River Infrastructure wrote to the Opportunities NB minister in a letter dated April 28 asking for 50 megawatts of power for a “large-scale data centre campus” that could include future expansion.

Meanwhile, the NB Power spokesperson said the 10 applications it has received will not necessarily be approved to connect to the grid. The spokesperson also said large projects like data centres would require contractual flexibility to protect the grid and avoid pressure on customer rates.

Thomas Bateman, a political science professor at St. Thomas University in Fredericton, said people are opposed to data centres, in part, because of anxiety about artificial intelligence.

“They don’t know if it’s good or bad — or if it’s going to mean the end of civilization as we know it, or if its going to cure cancer,” he said. Bateman added the other big point of contention is the amount of energy required to run the facillities.

A majority of Canadians aren’t sold on data centres, according to new polling from the non-profit Angus Reid Institute. 

The poll found 64 per cent of Canadians say their own respective provincial governments should limit the development of large data centres. Less than one in five people would encourage more, while the rest were not sure or couldn’t say.

The online survey was conducted from Sept. 8-16 among a representative randomized sample of Canadian adults who are members of the Angus Reid Forum. Online surveys cannot be assigned a margin of error because they do not randomly sample the population.

Canadian opposition to big data centres appears to be at odds with the federal Liberal government’s goals. Ottawa is promoting a major AI data-centre buildout as part of its sovereign-compute and digital-sovereignty agenda.

And despite the political pressure, some provincial governments haven’t shied away from capitalizing on the potential the big facilities have as a revenue stream.

Bell Canada is building what’s expected to be the country’s largest Canadian-owned data centre outside Regina, Sask. 

The $1.7-billion plant, which will use 300 megawatts of power from the provincial grid, was approved before Saskatchewan’s new framework was in place. 

In Alberta, Meta earlier this year announced a $13-billion-plus, one-gigawatt AI data centre in Sturgeon County, north of Edmonton. Hundreds of people protested against the project and the Alberta’s technology minister was booed at a round of town halls. 

Approaches have varied in Eastern Canada. 

In September, Nova Scotia Premier Tim Houston said his Progressive Conservative government would consider proposals from the sector due to changing conditions like geopolitics and Ottawa’s stance.

Meanwhile, Newfoundland and Labrador’s energy minister said the province could sell excess power to one.

In Quebec, the power utility is proposing to double the rates that data centres currently pay as large-power customers in the province.

A consultant hired by Hydro-Quebec also told a public hearing that energy consumption from data centres in North America could increase by 133 per cent between 2024 and 2030.

This report by The Canadian Press was first published Oct. 19, 2026.

— With files from Jeremy Simes in Regina and Lauren Krugel in Calgary.

Report Error Submit a Tip

More Stories

Letters, Oct. 23

7 minute read 2:00 AM CDT

People over cars — always

Re: Researchers: lights at crossing ‘long overdue’ (Oct. 22)

Maggie Macintosh’s article was right on the mark. The biggest problem with pedestrian crossings is the remarkable inconsistency, but there is also the fact that drivers at every traffic light are trained to keep running through amber lights until they turn to red.

I use the pedestrian crossing at Roblin Boulevard and Hunterspoint Road and drive through it every day. Almost every day I see drivers, from a full block away, who will just keep going through the flashing ambers (at the crossing), especially if there is traffic ahead of them doing the same thing.

Family history, solo sojourns paved path for celebrated author’s latest novel

Ben Sigurdson 7 minute read Preview

Family history, solo sojourns paved path for celebrated author’s latest novel

Ben Sigurdson 7 minute read 2:01 AM CDT

It’s 1967 and Lee Clarke has just been kicked out of UCLA when he receives his draft letter in the mail. Rather than report for basic training, he hops in a car and sets off across America on an amphetamine-fuelled road trip to bid farewell to his fractured, dysfunctional family before crossing the border into Canada.

Such is the premise for B.C.-born, Portland-based Patrick deWitt’s sixth novel Dodge City, published in September by House of Anansi. He’s in Winnipeg tonight at McNally Robinson Booksellers’ Grant Park location to launch the book.

The 51-year-old deWitt came to prominence with his sophomore novel, 2011’s The Sisters Brothers. The book was a critical and commercial success, winning the author the Governor General’s Literary Award for Fiction, the Rogers Writers’ Trust Fiction Prize and the Stephen Leacock Medal for Humour, and was adapted for the big screen in a film starring John C. Reilly and Joaquin Phoenix.

His 2018 novel French Exit was also adapted for cinema, and his 2023 novel The Librarianist won deWitt the Leacock Medal for the second time. Dodge City is deWitt’s fourth novel to make the Giller Prize long list.

Read
2:01 AM CDT

Masked, armed robbers terrorize elderly residents inside Crestview home

Erik Pindera 3 minute read Yesterday at 3:13 PM CDT

Several masked and armed suspects forced their way into a home on Lake Ridge Road in Winnipeg’s west suburbs late on Monday, terrorizing the elderly residents as they robbed the place.

Winnipeg Police Service major crimes investigators, who are asking the public for assistance, are trying to identify the suspects and learn about their movements in the area before and after the robbery, said police spokesman Const. Stephen Spencer.

“It would definitely help to have some more information as to who the individuals are. It would be great if somebody had video of the individuals prior to arriving at this location, when they weren’t wearing face coverings, or after,” said Spencer.

“If neighbours in the area maybe noticed something suspicious, around the Lakeridge Park area… around that time of night, if they did see something suspicious, definitely come forward — it could be helpful with solving this case.”

Henderson crosswalk has glaring safety gap, say researchers months after pedestrian killed

Maggie Macintosh 5 minute read Preview

Henderson crosswalk has glaring safety gap, say researchers months after pedestrian killed

Maggie Macintosh 5 minute read Yesterday at 2:00 AM CDT

Six months after a fatal collision at a crosswalk on Henderson Highway, two traffic safety researchers question why the intersection remains an outlier that is missing key flashing lights.

The City of Winnipeg is being urged to install “backflashers” to better protect road users moving in all directions at the intersection where a 32-year-old father died in the spring.

“It’s these little, mundane, non-sexy engineering problems that can cause everything right up to fatality,” said Curt Pankratz, an associate professor at the University of Winnipeg who studies traffic engineering and policymaking.

On April 19, shortly before sunrise, Gabe Beardy was struck when he was crossing the six-lane thoroughfare at Neil Avenue.

Read
Yesterday at 2:00 AM CDT

Living a lie takes a toll on whole family

Maureen Scurfield 4 minute read Yesterday at 2:00 AM CDT

Dear Miss Lonelyhearts: My wife is no longer my life partner! To my mind, she’s just the mother of my children. She still lives with us and does the major part of the child care.

This summer she discovered I had a girlfriend, but she didn’t want to “break up our family,” as I earn a lot of money. Now she’s treating me like garbage. She’s pleasant to the kids and our cleaning help, but she doesn’t speak much to me, and is disposed to giving me lists for groceries and medication pickups via email, so I pay for almost everything.

The kids seem fine so far, because we haven’t broken up our family and we haven’t changed how we treat each other in front of them. We’re polite and we never fight.

Then just last weekend, my wife finally let me know she’d recently met someone she’s “seeing privately.” It’s a guy we both know from a sports activity the kids enjoy. That just makes me sick — and is upsetting me far more than breaking up.

Builder beefs up security after string of blazes

Morgan Modjeski 3 minute read 2:01 AM CDT

A Winnipeg builder said he’s had to beef up security around his developments after one of his projects sustained significant damage Wednesday in suspected arson cases.

“This is so bad for me,” said Rupinder Brar. “This is so sad.”

Firefighters were sent to the construction site at 297 Regal Ave., shortly before 4 a.m. Heavy smoke and flames were coming from the two homes on the site and threatened to jump to nearby buildings.

Winnipeg Police Service Const. Claude Chancy said police are investigating the blaze, as well as two fires in St. Boniface that were five days apart.