Curtain finally rising on the Met makeover
Advertisement
Read this article for free:
or
Already have an account? Log in here »
To continue reading, please subscribe:
Digital Subscription
One year of digital access for only $205*
- Enjoy unlimited reading on winnipegfreepress.com
- Read the E-Edition, our digital replica newspaper
- Access News Break, our award-winning app
- Play interactive puzzles
*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.
To continue reading, please subscribe:
Add Free Press access to your Brandon Sun subscription for only an additional
$1 for the first 4 weeks*
- Enjoy unlimited reading on winnipegfreepress.com
- Read the E-Edition, our digital replica newspaper
- Access News Break, our award-winning app
- Play interactive puzzles
*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.
Read unlimited articles for free today:
or
Already have an account? Log in here »
Hey there, time traveller!
This article was published 23/09/2009 (6144 days ago), so information in it may no longer be current.
THE long-awaited restoration and redevelopment of downtown’s historic Metropolitan Theatre is finally underway.
A work crew began cleaning the exterior brickwork on the 90-year-old Donald Street building Monday as part of Phase 1 of the project.
Over the next couple of months, workers will be cleaning and repairing the exterior bricks, installing new glass in the windows, stripping off the old paint and returning the facade to its original glory, said Loretta Martin, spokeswoman for CentreVenture Development Corp., the city’s downtown development agency.
Martin said Phase 2 will involve restoration and redevelopment of the interior, the demolition of a one-storey building on the south side of the theatre and construction of an addition there.
She said the building’s owner, the Canad Inns hotel chain, has not yet submitted its final plans for the Phase 2 work, "but by Oct. 5 or 6 we should have a timeline for everything… and the details of what they’re going to do."
Canad Inns CEO Taras Sokolyk said the final details are still being worked out, partly because the situation is constantly changing.
"I know it’s taken a ton of time… but as we dig deeper into the building, we find some unique things that we want to save or find some additional things need to be replaced," he said.
The Winnipeg-based company purchased the Met from CentreVenture in 2006 for $100,000. Renovations to the building, which has sat empty since 1987, originally were supposed to get underway before the end of 2007 and be completed by June this year.
But that never happened, and in an interview last March, Canada Inns president and chairman Leo Ledohowski said the revised plans were to begin the work this past spring.
When that also didn’t happen, rumblings began to surface last month that CentreVenture officials were thinking of taking back the building. However, Canad Inns issued a statement saying the work would start within a few weeks.
"We’re very pleased to see it underway," Martin said.
In the interview last March, Ledohowski said Canad Inns plans to remove the theatre seats and convert the theatre into a "super supper club" featuring food, beverages and entertainment. It will also cater to some special events, such as high school grads and fundraising dinners, and may operate one night a week as a nightclub.
He also said he expected the project to cost more than $10 million. Canad Inns said last month it has already spent $500,000 on interior renovations.