Yukon mine receiver sues Vancouver firm for negligence linked to 2024 collapse

Advertisement

Advertise with us

VANCOUVER - The receiver of a defunct Yukon gold mine that suffered a catastrophic storage site failure in 2024 is suing a Vancouver mining engineering company for its alleged role in the disaster.

Read this article for free:


or

Already have an account? Log in here »

To continue reading, please subscribe:

Subscribe and receive a limited-edition Free Press branded hat or tote.

Digital Subscription

One year of digital access for only $205*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.

To continue reading, please subscribe:

Add Free Press access to your Brandon Sun subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Start now

*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

VANCOUVER – The receiver of a defunct Yukon gold mine that suffered a catastrophic storage site failure in 2024 is suing a Vancouver mining engineering company for its alleged role in the disaster.

PricewaterhouseCoopers says in a civil claim filed in B.C. Supreme Court on June 19 that JDS Energy and Mining Inc. provided construction and engineering services to the mine for years, and allegedly made “critical errors” in the lead up to the failure. 

The lawsuit stems from a heap leach pad failure at the Eagle Gold Mine near Mayo, Yukon, on June 24, 2024, where about two million tonnes of cyanide-soaked ore spilled into the local environment, including in fish-bearing water bodies. 

The Law Courts building, which is home to B.C. Supreme Court and the Court of Appeal, is seen in Vancouver, on Thursday, Nov. 23, 2023. THE CANADIAN PRESS/Darryl Dyck
The Law Courts building, which is home to B.C. Supreme Court and the Court of Appeal, is seen in Vancouver, on Thursday, Nov. 23, 2023. THE CANADIAN PRESS/Darryl Dyck

PricewaterhouseCoopers says in the lawsuit that JDS provided services to Victoria Gold over more than a decade, including consultation, producing studies and construction management at the Eagle mine linked to the ore storage site.

It alleges that the Vancouver company did not properly consult Victoria Gold on practices such as making sure fluids would properly drain from the site, leading to weak layers within the storage facility that triggered the slide.

No one from JDS was immediately available to comment on the lawsuit and the company has not filed a legal response. 

The action says JDS failed to address the risks of year-round ore stacking in a cold climate. 

“Earlier feasibility studies had recommended limiting ore stacking to 250 days per year during the warmest nine months of the year to avoid the creation of frozen patches within the heap, and had specified heating of leaching solution and burial of irrigation lines. 

“Year-round stacking was subsequently adopted following its endorsement in the 2022 Technical Report, which, as noted above, JDS was involved in preparing,” the lawsuit says. 

This report by The Canadian Press was first published June 24, 2026.