Rough seas cause construction challenges at AltaGas export facility in B.C.
Advertisement
Read this article for free:
or
Already have an account? Log in here »
To continue reading, please subscribe:
Digital Subscription
One year of digital access for only $205*
- Enjoy unlimited reading on winnipegfreepress.com
- Read the E-Edition, our digital replica newspaper
- Access News Break, our award-winning app
- Play interactive puzzles
*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.
To continue reading, please subscribe:
Add Free Press access to your Brandon Sun subscription for only an additional
$1 for the first 4 weeks*
- Enjoy unlimited reading on winnipegfreepress.com
- Read the E-Edition, our digital replica newspaper
- Access News Break, our award-winning app
- Play interactive puzzles
*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.
Read unlimited articles for free today:
or
Already have an account? Log in here »
CALGARY – Rough seas have been posing challenges for AltaGas Ltd. as construction on its propane and butane export terminal on British Columbia’s north coast nears completion.
The Ridley Island Energy Export Facility, or REEF, is 85 per cent complete and on track to come online before the end of March 2027, the company said Thursday as it reported its second-quarter results.
REEF’s capital cost estimate has risen by 12 per cent to about $1.5 billion.
“While onshore execution has been ahead of plan, in-water construction has proven more challenging due to maritime conditions and weather delays,” chief executive Vern Yu told analysts on a conference call.
“Since we started in-water construction at REEF in the fall of 2024, we have lost over 450 rig days due to extreme weather, extreme ocean swells and marine mammal activity. These lost rig days significantly exceeded any normal contingency plan. As a result, onshore efficiencies are no longer expected to fully offset higher in-water construction costs.”
The jetty and loading platform are 80 per cent complete at the site in Prince Rupert, B.C., and most of the remaining in-water work is set to wrap over the next six weeks.
“With the in-water phase of construction, the most complex and challenging part of REEF, nearing-completion, we’re highly confident that we’ll be able to meet a revised cost estimate and schedule,” Yu said.
Also Thursday, AltaGas reported $288 million in net income applicable to common shares, up from $175 million in the same quarter last year.
The profit amounted to 92 cents per diluted share for the quarter ended June 30, up from 58 cents per diluted share in the same period last year.
Revenue for the quarter totalled $3.8 billion, an increase from $2.84 billion in the second quarter of 2025.
AltaGas raised its guidance for capital spending for 2026 to $1.8 billion from $1.7 billion.
The company also said it now expects normalized earnings per share of $2.35 to $2.60, an increase of six per cent.
This report by The Canadian Press was first published July 30, 2026.