Sewage plant upgrade on budget despite two-year delay
Advertisement
Read this article for free:
or
Already have an account? Log in here »
To continue reading, please subscribe:
Digital Subscription
One year of digital access for only $205*
- Enjoy unlimited reading on winnipegfreepress.com
- Read the E-Edition, our digital replica newspaper
- Access News Break, our award-winning app
- Play interactive puzzles
*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.
To continue reading, please subscribe:
Add Free Press access to your Brandon Sun subscription for only an additional
$1 for the first 4 weeks*
- Enjoy unlimited reading on winnipegfreepress.com
- Read the E-Edition, our digital replica newspaper
- Access News Break, our award-winning app
- Play interactive puzzles
*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.
Read unlimited articles for free today:
or
Already have an account? Log in here »
Hey there, time traveller!
This article was published 16/01/2017 (3499 days ago), so information in it may no longer be current.
A $336-million upgrade to the south end sewage treatment plant is on budget but two years behind schedule.
Officials from the water and waste department told the finance committee Monday that a series of setbacks have pushed the project’s completion date from 2019 to 2021.
Geoff Patton, the department’s manager of engineering, said the delays are unavoidable but added they’re not expected to increase the cost of the project.
The south end plant is being upgraded to handle additional effluent flows and to meet stringent new provincial regulations for phosphorous and nitrogen discharges into the Red River.
Patton said a one-year delay was caused by the failure of the engineering consulting firm working on the project to submit drawings within the expected timeline.
The firm presented the department with a 4,000-page report, including 1,700 technical drawings on Dec. 24, Patton said, adding the report must be closely vetted before any contracts can be put out for tender.
Patton said another year’s delay has been caused by the need to review the proposed change in the construction schedule.
While project delays usually result in contract increases, Patton said the department has been talking to construction firms eager for the work and it doesn’t seem likely the estimates will vary much.
The project’s estimated price tag of $336 million includes a range of between $269.5 million and $436.3 million.