Nova Scotia judge rules minister’s approval of wind farm project was reasonable
Advertisement
Read this article for free:
or
Already have an account? Log in here »
To continue reading, please subscribe:
Digital Subscription
One year of digital access for only $205*
- Enjoy unlimited reading on winnipegfreepress.com
- Read the E-Edition, our digital replica newspaper
- Access News Break, our award-winning app
- Play interactive puzzles
*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.
To continue reading, please subscribe:
Add Free Press access to your Brandon Sun subscription for only an additional
$1 for the first 4 weeks*
- Enjoy unlimited reading on winnipegfreepress.com
- Read the E-Edition, our digital replica newspaper
- Access News Break, our award-winning app
- Play interactive puzzles
*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.
Read unlimited articles for free today:
or
Already have an account? Log in here »
Hey there, time traveller!
This article was published 26/01/2024 (965 days ago), so information in it may no longer be current.
HALIFAX – A Nova Scotia judge has upheld the provincial environment minister’s approval of a 17-turbine wind farm in the Wentworth Valley.
In a written decision released Wednesday, Nova Scotia Supreme Court Justice Timothy Gabriel ruled that Environment Minister Tim Halman’s decision was reasonable and was based on all of the information he was required to consider.
Halman gave conditional approval to the Higgins Mountain project on May 4 of last year and was subsequently challenged in court by a community group, Project Wentworth Valley.
Gabriel noted that the court’s review of the minister’s approval took into account the fact the minister has been “legislatively entrusted to make the decision in question.”
“This is not to say that the review is a ‘rubber stamp’ by any means,” wrote Gabriel. “The process remains robust. It is not, however, as some authorities have pointed out, a treasure hunt for error.”
Project Wentworth Valley launched the court case saying it believed Halman didn’t take into account the concerns of area residents. Specifically, it contended that the minister failed to adequately address the wind farm’s impact on mainland moose and the community’s use of the area for outdoor recreation and ecotourism.
But the court decision says Halman considered a 260-page assessment of the project, more than 2,700 pages of scientific and other documents along with public input and information through a consultation with Nova Scotia Mi’kmaq before granting approval.
Gabriel said the community group couched its criticisms of Halman’s decision in terms stating that he failed to “adequately consider” factors under Section 12 of the province’s Environmental Assessment Regulations. The section sets out the information that “shall be” considered by the minister.
The judge explained the group concluded that Halman acted unreasonably in deciding the terms in his decision “would adequately mitigate” the wind farm’s adverse effects on species at risk, including the mainland moose.
“First and with respect, this is nothing more than an attempt to subject the minister to a ‘correctness’ standard, which … is inapplicable here. The minister is not required to do any more than ‘consider’ the factors under Section 12.”
Gabriel added that the minister is also not required to measure up to a standard the applicant or anyone else “might consider to be adequate.”
“The applicant has not demonstrated that the minister’s decision, with attached conditions, was an unreasonable one,” the judge concluded. “As a consequence, this application is dismissed.”
In an emailed statement, Halman said he was pleased with a court decision that “speaks for itself” as to the thoroughness of Nova Scotia’s environmental assessment process.
“As the neutral regulator, my job is to protect the environment and ensure our processes are followed,” Halman said. “I take that seriously. Nova Scotians can have confidence in that.”
A representative from Project Wentworth was not immediately available for comment.
The Higgins Mountain project would erect turbines between the communities of Westchester Station, Wentworth Station and Londonderry in north-central Nova Scotia. Construction is expected to begin this year, with the project expected to be operational for 35 years beginning in 2025.
Under the province’s conditional approval, the project must do noise modelling and formulate management plans for water and erosion and for the potential effects on wildlife and birds. A monitoring plan is also required for mainland moose for at least two years.
This report by The Canadian Press was first published Jan. 26, 2024.