Future data centers are driving up forecasts for energy demand. States want proof they’ll get built

Advertisement

Advertise with us

HARRISBURG, Pa. (AP) — The forecasts are eye-popping: utilities saying they'll need two or three times more electricity within a few years to power massive new data centers that are feeding a fast-growing AI economy.

Read this article for free:


or

Already have an account? Log in here »

To continue reading, please subscribe:

Subscribe and receive a limited-edition Free Press branded hat or tote.

Digital Subscription

One year of digital access for only $205*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.

To continue reading, please subscribe:

Add Free Press access to your Brandon Sun subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Start now

*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

Hey there, time traveller!
This article was published 14/11/2025 (284 days ago), so information in it may no longer be current.

HARRISBURG, Pa. (AP) — The forecasts are eye-popping: utilities saying they’ll need two or three times more electricity within a few years to power massive new data centers that are feeding a fast-growing AI economy.

But the challenges — some say the impossibility — of building new power plants to meet that demand so quickly has set off alarm bells for lawmakers, policymakers and regulators who wonder if those utility forecasts can be trusted.

One burning question is whether the forecasts are based on data center projects that may never get built — eliciting concern that regular ratepayers could be stuck with the bill to build unnecessary power plants and grid infrastructure at a cost of billions of dollars.

This stretch of land between the Conodoguinet Creek and Country Club Road near Carlisle, Pennsylvania, is in the planning stages to become a $15 billion data center complex, Friday Nov. 14, 2025, in Carlisle, Pa. (AP Photo/Marc Levy)
This stretch of land between the Conodoguinet Creek and Country Club Road near Carlisle, Pennsylvania, is in the planning stages to become a $15 billion data center complex, Friday Nov. 14, 2025, in Carlisle, Pa. (AP Photo/Marc Levy)

The scrutiny comes as analysts warn of the risk of an artificial intelligence investment bubble that’s ballooned tech stock prices and could burst.

Meanwhile, consumer advocates are finding that ratepayers in some areas — such as the mid-Atlantic electricity grid, which encompasses all or parts of 13 states stretching from New Jersey to Illinois, as well as Washington, D.C. — are already underwriting the cost to supply power to data centers, some of them built, some not.

“There’s speculation in there,” said Joe Bowring, who heads Monitoring Analytics, the independent market watchdog in the mid-Atlantic grid territory. “Nobody really knows. Nobody has been looking carefully enough at the forecast to know what’s speculative, what’s double-counting, what’s real, what’s not.”

Suspicions about skyrocketing demand

There is no standard practice across grids or for utilities to vet such massive projects, and figuring out a solution has become a hot topic, utilities and grid operators say.

Uncertainty around forecasts is typically traced to a couple of things.

One concerns developers seeking a grid connection, but whose plans aren’t set in stone or lack the heft — clients, financing or otherwise — to bring the project to completion, industry and regulatory officials say.

Another is data center developers submitting grid connection requests in various separate utility territories, PJM Interconnection, which operates the mid-Atlantic grid, and Texas lawmakers have found.

Often, developers, for competitive reasons, won’t tell utilities if or where they’ve submitted other requests for electricity, PJM said. That means a single project could inflate the energy forecasts of multiple utilities.

The effort to improve forecasts got a high-profile boost in September, when a Federal Energy Regulatory Commission member asked the nation’s grid operators for information on how they determine that a project is not only viable, but will use the electricity it says it needs.

“Better data, better decision-making, better and faster decisions mean we can get all these projects, all this infrastructure built,” the commissioner, David Rosner, said in an interview.

The Edison Electric Institute, a trade association of for-profit electric utilities, said it welcomed efforts to improve demand forecasting.

Real, speculative, or ‘somewhere in between’

The Data Center Coalition, which represents tech giants like Google and Meta and data center developers, has urged regulators to request more information from utilities on their forecasts and to develop a set of best practices to determine the commercial viability of a data center project.

The coalition’s vice president of energy, Aaron Tinjum, said improving the accuracy and transparency of forecasts is a “fundamental first step of really meeting this moment” of energy growth.

“Wherever we go, the question is, ‘Is the (energy) growth real? How can we be so sure?’” Tinjum said. “And we really view commercial readiness verification as one of those important kind of low-hanging opportunities for us to be adopting at this moment.”

Igal Feibush, the CEO of Pennsylvania Data Center Partners, a data center developer, said utilities are in a “fire drill” as they try to vet a deluge of data center projects all seeking electricity.

The vast majority, he said, will fall off because many project backers are new to the concept and don’t know what it takes to get a data center built.

States also are trying to do more to find out what’s in utility forecasts and weed out speculative or duplicative projects.

In Texas, which is attracting large data center projects, lawmakers still haunted by a blackout during a deadly 2021 winter storm were shocked when told in 2024 by the grid operator, the Electric Reliability Council of Texas, that its peak demand could nearly double by 2030.

They found that state utility regulators lacked the tools to determine whether that was realistic.

Texas state Sen. Phil King told a hearing earlier this year that the grid operator, utility regulators and utilities weren’t sure if the power requests “are real or just speculative or somewhere in between.”

Lawmakers passed legislation sponsored by King, now law, that requires data center developers to disclose whether they have requests for electricity elsewhere in Texas and to set standards for developers to show that they have a substantial financial commitment to a site.

Electricity bills are rising, too

PPL Electric Utilities, which delivers power to 1.5 million customers across central and eastern Pennsylvania, projects that data centers will more than triple its peak electricity demand by 2030.

Vincent Sorgi, president and CEO of PPL Corp., told analysts on an earnings call this month that the data center projects “are real, they are coming fast and furious” and that the “near-term risk of overbuilding generation simply does not exist.”

The data center projects counted in the forecast are backed by contracts with financial commitments often reaching tens of millions of dollars, PPL said.

Still, PPL’s projections helped spur a state lawmaker, Rep. Danilo Burgos, to introduce a bill to bolster the authority of state utility regulators to inspect how utilities assemble their energy demand forecasts.

Ratepayers in Burgos’ Philadelphia district just absorbed an increase in their electricity bills — attributed by the utility, PECO, to the rising cost of wholesale electricity in the mid-Atlantic grid driven primarily by data center demand.

That’s why ratepayers need more protection to ensure they are benefiting from the higher cost, Burgos said.

“Once they make their buck, whatever company,” Burgos said, “you don’t see no empathy towards the ratepayers.”

___

Follow Marc Levy at http://twitter.com/timelywriter.

Report Error Submit a Tip

More Stories

Making a clear code of conduct for Winnipeg councillors

Editorial 4 minute read Preview

Making a clear code of conduct for Winnipeg councillors

Editorial 4 minute read Yesterday at 2:00 AM CDT

As Winnipeggers have recently been reminded in the case of Transcona city councillor Russ Wyatt, not all codes of conduct are created equal.

Read
Yesterday at 2:00 AM CDT

Today’s horoscope

Georgia Nicols 4 minute read Preview

Today’s horoscope

Georgia Nicols 4 minute read 2:00 AM CDT

MOON ALERT: After 4:30 a.m. there are no restrictions to shopping or important decisions today. The moon is in Aquarius.

ARIES (March 21-April 19)

Your interactions with friends and members of groups might be intense. Someone might do something that catches you off-guard. Or perhaps, you’ll meet someone unusual? Very likely, you’ll feel sympathetic for someone else, and you might look for ways to help them.

TAURUS (April 20-May 20)

Read
2:00 AM CDT

Driver, 21, killed in Interlake crash

1 minute read Yesterday at 11:44 AM CDT

A 21-year-old Thompson man was killed in a crash in the Interlake on Sunday.

RCMP said a southbound truck went into a ditch on Highway 6, just north of Moosehorn, and rolled multiple times at about 5 a.m.

The 21-year-old man, who died at the scene, was driving the truck, police said.

Six passengers suffered non-life-threatening injuries. A STARS air ambulance was called to the scene.

Ottawa to announce details of retaliatory tariffs on U.S. Tuesday

Nick Murray and Catherine Morrison, The Canadian Press 6 minute read Preview

Ottawa to announce details of retaliatory tariffs on U.S. Tuesday

Nick Murray and Catherine Morrison, The Canadian Press 6 minute read Updated: Yesterday at 7:08 PM CDT

OTTAWA - The federal government is set to unveil details of Canada's retaliatory tariffs against the United States on Tuesday.

Finance Minister François-Philippe Champagne, Industry Minister Mélanie Joly, Jobs Minister Patty Hajdu and Artificial Intelligence Minister Evan Solomon are also expected to share details of supports for workers affected by tariffs.

Solomon is also the minister responsible for the Federal Economic Development Agency for Southern Ontario.

Communities on both sides of the Canada-U.S. border have been affected by the ongoing trade war. 

Read
Updated: Yesterday at 7:08 PM CDT

A bigger grid, and a tougher one

Stuart Williams 5 minute read Preview

A bigger grid, and a tougher one

Stuart Williams 5 minute read 2:00 AM CDT

The Free Press editorial of Aug. 21, Time for a stronger Canadian grid, makes a case that should unsettle anyone who read it.

A co-ordinated attack on nine substations could bring down the American electrical grid.

The transformers needed to repair it carry lead times of 128 weeks and longer, from countries on the U.S. president’s tariff list.

And because the North American system is effectively one machine, a fault in Ohio once darkened Toronto.

Read
2:00 AM CDT

A bad trade deal in virtually all ways

Editorial 4 minute read Preview

A bad trade deal in virtually all ways

Editorial 4 minute read 2:01 AM CDT

You can’t fix stupid.

And you can’t sign a contract — or a trade deal — with a proven liar, cheat and blackmailer.

And sometimes, you end up having to fight.

Yes, we are referring to U.S. President Donald Trump, a politician who obviously confuses might with bright.

Read
2:01 AM CDT