Cost of reopening Portage and Main expected to jump by $8 million

Reopening Portage and Main to pedestrians is set to cost the city $8 million more than expected, a new report says.

Read this article for free:


or

Already have an account? Log in here »

To continue reading, please subscribe:

Subscribe and receive a limited-edition Free Press branded hat or tote.

Digital Subscription

One year of digital access for only $205*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.

To continue reading, please subscribe:

Add Free Press access to your Brandon Sun subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Start now

*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

Hey there, time traveller!
This article was published 01/11/2024 (682 days ago), so information in it may no longer be current.

Reopening Portage and Main to pedestrians is set to cost the city $8 million more than expected, a new report says.

In March, city council voted to open pedestrian crossing at the intersection in 2025, budgeting $13 million for the work. However, the city has since received just one bid on the project, which will raise the overall price to $21.3 million.

“The additional budget is attributed to an aggressive schedule requiring significant labour and risk to complete it on time, the requirements of sub-contractor works requiring significant oversight, complex interaction between public right-of-way and private properties, and that construction will primarily occur over the winter months, which brings several logistical challenges,” Brad Neirinck, manager of engineering for public works, wrote in the report.

MIKAELA MACKENZIE / FREE PRESS
                                Lane closures and construction at Portage and Main in October.

MIKAELA MACKENZIE / FREE PRESS

Lane closures and construction at Portage and Main in October.

Neirinck notes the intersection “must be opened” to pedestrians by the time Winnipeg Transit begins to overhaul its network, which is expected to begin on June 29.

The report calls for the public works committee to award the contract to M.D. Steele Construction Ltd.

It also notes a consultant warned it would be difficult to pin down the project’s price.

“Due to the unique nature of the project, it was challenging to calculate an estimate for it as there were no comparable projects to refer to,” wrote Neirinck.

‘Short-term pain for longer-term gain’

Mayor Scott Gillingham said he supports a staff proposal to cover the significant cost hikes through transfers from the road renewal and downtown streets budgets, so the work can be done on time.

“It will be an aggressive timeline with construction in the dead of winter — which doesn’t always happen — at the corner of Portage and Main. There are obviously increased costs associated with the type of very unique project that it is,” said Gillingham.

The mayor said he isn’t concerned taking money out of the roads budget will lead other projects to be cancelled.

“My understanding is the projects wouldn’t be lost but simply deferred,” he said.

MIKAELA MACKENZIE / FREE PRESS 
                                The city aims to open the intersection to pedestrians by the time Winnipeg Transit begins to overhaul its network, which is expected to begin on June 29.

MIKAELA MACKENZIE / FREE PRESS

The city aims to open the intersection to pedestrians by the time Winnipeg Transit begins to overhaul its network, which is expected to begin on June 29.

Reopening Portage and Main to pedestrians has proven divisive for years. While 65 per cent of Winnipeggers voted against the idea in a 2018 plebiscite, Gillingham said the option is better than spending $73 million to repair a membrane to renovate the site’s underground concourse.

“What we’ve got here is short-term pain for longer-term gain,” he said.

The mayor has called for the underground concourse to close. The city is set to commission a study on how that could occur, which council will then consider.

Access essential for transit overhaul

Pedestrian traffic has not been allowed at the intersection since 1979. The mayor stressed it is essential that access is restored in time for Winnipeg Transit’s route overhaul.

“With the change of the transit network, all major lines are going to go through Portage and Main. If we delayed this project… we would do the changeover to the new network and then immediately slow the network down with construction at Portage and Main,” said Gillingham.

Maps of Winnipeg's proposed new transit routes
The City of Winnipeg will be revamping the city

Coun. Janice Lukes, chairwoman of public works, said she also supports covering the rising cost of the project.

“When you’re (building) something… in the winter and, when you’re doing it in a shortened timeline, there’s a risk element in it,” said Lukes (Waverley West).

“It’s also a high-profile project. I know companies that didn’t want to bid on it because it was a high-profile project (and) because it was (in) the winter.”

‘We have better things to do’

Not all councillors think the project is worth its rising price.

Coun. Jeff Browaty, who serves as finance chairman, said he remains opposed to the change because he thinks adding foot traffic will create significant traffic delays. Browaty (North Kildonan) said he is also concerned about the increased cost.

“It’s pretty (concerning) how much over the budget it is. And it would be interesting (to see) if there’s any good estimates as to what it would cost to do regular-season construction (instead),” he said.

Coun. Russ Wyatt said he opposes covering the cost hike, arguing the cash-strapped city has much more pressing priorities to fund.

“The city should reverse the decision (to reopen). We have better things to do in this city than talk about Portage and Main. We’ve got a whole mental-health and addictions crisis… we have our infrastructure crumbling, we’ve got Arlington Bridge closed,” said Wyatt (Transcona).

MIKAELA MACKENZIE / FREE PRESS 
                                Reopening Portage and Main to pedestrians has proven divisive for years.

MIKAELA MACKENZIE / FREE PRESS

Reopening Portage and Main to pedestrians has proven divisive for years.

The cost hike requires only the approval of the standing policy committee on public works, not a full council vote.

After a Nov. 6 meeting to determine the latest round of standing policy committee members, Lukes expects to continue to chair the committee, alongside councillors Devi Sharma, Ross Eadie and Markus Chambers as its other members.

‘Sends some pretty big red flags’

Coun. Evan Duncan said he hasn’t decided if he supports covering the cost hike.

“This sends some pretty big red flags up in the air that, potentially, the folks that are ballparking these costs for us are not doing a great job at it,” said Duncan (Charleswood-Tuxedo-Westwood).

He also criticized the project’s timing.

“The timing on it is obviously garbage. Going through winter months is going to be extremely expensive,” said Duncan.

A request to interview city staff about the cost hike was not granted Friday. In an email, communications director Felicia Wiltshire noted the same rationale for the hike that was noted in the staff report, including the desire to support the Transit overhaul in June.

“Retendering the work for summer construction only would result in earliest completion in late Fall 2025,” wrote Wiltshire.

The public works committee is expected to vote on the matter Thursday.

joyanne.pursaga@freepress.mb.ca

X: @joyanne_pursaga

Joyanne Pursaga

Joyanne Pursaga
Reporter

Joyanne is city hall reporter for the Winnipeg Free Press. A reporter since 2004, she began covering politics exclusively in 2012, writing on city hall and the Manitoba Legislature for the Winnipeg Sun before joining the Free Press in early 2020. Read more about Joyanne.

Every piece of reporting Joyanne produces is reviewed by an editing team before it is posted online or published in print — part of the Free Press‘s tradition, since 1872, of producing reliable independent journalism. Read more about Free Press’s history and mandate, and learn how our newsroom operates.

Our newsroom depends on a growing audience of readers to power our journalism. If you are not a paid reader, please consider becoming a subscriber.

Our newsroom depends on its audience of readers to power our journalism. Thank you for your support.

History

Updated on Friday, November 1, 2024 4:24 PM CDT: Story completely updated with more information.

Report Error Submit a Tip

More Stories

Citizen reports help highlight connectivity issues across southwest Manitoba

Nicole Buffie 5 minute read Preview

Citizen reports help highlight connectivity issues across southwest Manitoba

Nicole Buffie 5 minute read Saturday, Sep. 12, 2026

A southwestern Manitoba man has created a map to document cell service blackout spots in an effort to push for better access in rural areas.

Mark Custance compiled more than 300 citizen reports over the last few months to document where service in southwest Manitoba is strong, spotty or doesn’t exist at all.

“I’ve heard people complain and say, ‘cell service sucks’ or ‘this is not working.’ But what does the data actually say?” Custance said from his office in Melita, where he has installed a cell-service booster to maintain connectivity with the rest of the world.

Analyzing where service is good and poor, he cross-references it with the location of cellphone towers across the region.

Read
Saturday, Sep. 12, 2026

Pokemon thieves clear out collectibles shop

Scott Billeck 5 minute read Preview

Pokemon thieves clear out collectibles shop

Scott Billeck 5 minute read Friday, Sep. 11, 2026

Terri Settle loved watching children walk into her collectibles shop to hunt for their favourite Pokemon cards.

After the latest break in stripped her shelves of much of the inventory, she’s not sure she’ll get to see it again.

Thieves broke into Terri’s Trinkets and Toys on Tuesday evening, punching through a grate and then the store’s bathroom wall to reach the storefront.

They made off with about $6,000 worth of merchandise, including all of the store’s Pokemon cards — about 7,000 of them — along with toys, Lego, jewelry, video games, a debit machine and personal laptop. They even took her vacuum cleaner.

Read
Friday, Sep. 11, 2026

Bombers exact revenge in Banjo Bowl, lose Collaros to injury

Taylor Allen 6 minute read Preview

Bombers exact revenge in Banjo Bowl, lose Collaros to injury

Taylor Allen 6 minute read Saturday, Sep. 12, 2026

Redha Kramdi downplayed the significance of his return for the Winnipeg Blue Bombers.

“I don’t think I have that big of an impact,” said Kramdi on Tuesday, who watched the club go 2-4 while he was sidelined with a cast on his left hand.

It sounded silly at the time, and it’s even sillier now considering how exceptional the 29-year-old safety from Montreal was in Saturday’s 22nd edition of the Banjo Bowl.

Kramdi caused two turnovers — a forced fumble and an interception — to lead the Bombers to a 19-6 victory over the Saskatchewan Roughriders in front of a sell-out crowd at Princess Auto Stadium.

Read
Saturday, Sep. 12, 2026

A man has been arrested and remains in police custody after being charged with spraying bear spray inside a Henderson Highway hotel in early July. The suspect is also accused of  pointing a gun, chasing people and making violent threats in the hotel's parking lot after a dispute over a VLT ticket at the licensed establishment in the 1000 block of Henderson Highway.

Matthew Joseph Marriott, 33, was arrested Sept. 10, the Winnipeg Police Service stated in a news release Sunday. He is charged with several firearms and weapons offences as well as possession of heroin.

Police say the suspect discharged a canister of bear spray at a 36-year-old man and into the bar area of the Curtis Gordon Hotel before going into the parking lot and pointing a gun at people. The firearm was determined to be an airgun, a Sig Sauer MCX. Officers found it on scene, in a backpack, after the suspect fled. The backpack also contained bear spray a knife and a small quantity of suspected heroin, the news release stated.

Sunday-night auto aficionados work to steer away from unwelcome elements they say aren’t a part of their tradition

Zoe Pierce 12 minute read Preview

Sunday-night auto aficionados work to steer away from unwelcome elements they say aren’t a part of their tradition

Zoe Pierce 12 minute read Friday, Sep. 11, 2026

The red 1969 Dodge Coronet Super Bee out for a cruise on Portage Avenue draws admiring eyes from onlookers on a recent Sunday night, many of them seeing a specimen of the now-rare muscle car for the first time on a Winnipeg street. Or any other street, for that matter.

Longtime car enthusiast Bob Sudoma was behind the wheel, participating in the decades-old show-offy summer tradition.

The Sunday night cruise is built around a simple idea: proud car owners take their beloved vehicles for a spin to meet up with others of the same autophile ilk.

Less-fortunate appreciators, or just curious folks, also gather along the route to watch the highly-polished parade. Portage Avenue is one of cruise night’s best-known stretches.

Read
Friday, Sep. 11, 2026

Cost of reopening Portage and Main expected to jump by $8 million

Joyanne Pursaga 3 minute read Preview

Cost of reopening Portage and Main expected to jump by $8 million

Joyanne Pursaga 3 minute read Friday, Nov. 1, 2024

The reopening of Winnipeg's Portage and Main intersection to pedestrians is projected to cost the city $21.3 million— $8 million over budget — due to logistical challenges and an aggressive schedule for winter construction.

Read
Friday, Nov. 1, 2024