Centre Block construction within cost, but Ottawa must make faster decisions: auditor
Advertisement
Read this article for free:
or
Already have an account? Log in here »
To continue reading, please subscribe:
Digital Subscription
One year of digital access for only $205*
- Enjoy unlimited reading on winnipegfreepress.com
- Read the E-Edition, our digital replica newspaper
- Access News Break, our award-winning app
- Play interactive puzzles
*First annual payment billed as $205.00 + GST for one year. This annual subscription will automatically renew at $233.00 + GST every 52 weeks (10% off the regular annual price of $259.35). Offer available to new and qualified returning subscribers only. Cancel any time.
To continue reading, please subscribe:
Add Free Press access to your Brandon Sun subscription for only an additional
$1 for the first 4 weeks*
- Enjoy unlimited reading on winnipegfreepress.com
- Read the E-Edition, our digital replica newspaper
- Access News Break, our award-winning app
- Play interactive puzzles
*Your next Brandon Sun subscription payment will increase by $1.00 and you will be charged $17.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.
Read unlimited articles for free today:
or
Already have an account? Log in here »
Hey there, time traveller!
This article was published 27/03/2023 (1212 days ago), so information in it may no longer be current.
OTTAWA – The modernization of Parliament’s Centre Block is within budget so far, but the federal government needs to do a better job at making up their minds before major construction begins, the federal auditor general says in a new report.
Karen Hogan warns in a report released Monday that if decision-making remains fragmented, it could lead to construction delays — and more costs for taxpayers.
The rehabilitation of Centre Block already comes with a price tag of up to $5 billion, and is set to be completed by 2031.
“Given the size and complexity of this undertaking, a streamlined decision-making process will be required to continue effectively managing the costs and timelines of the rehabilitation program, as construction work accelerates between now and the planned completion date,” reads the report, which covers the period from January 2010 until July 2022.
The government is responsible for deciding how it wants Centre Block to look, including how many office spaces, committee rooms and security measures are needed, the report says.
“All these elements are important to determine the construction cost and schedule of the program and to keep it on track,” it reads.
In response, the federal government said it will start submitting project reports to the Speakers of the House of Commons and Senate twice a year, and it has committed to undergo a study to ensure the space is inclusive.
Following the feedback, the government has already changed the design of a new ventilation system so that some traditional Indigenous ceremonial places can take place inside, such as smudging and the use of the qulliq, an oil lamp used by Indigenous Peoples in the Arctic.
Other design elements approved by the government include making the building resistant to earthquakes, determining the size of its welcome centre and making it more accessible to people with disabilities.
The construction of Centre Block as it stands today began in 1916, after a fire destroyed the original building, and wrapped up in 1927.
It housed the House of Commons and the Senate of Canada beginning 1922, and had had only minor repairs until its closure for the major renovations in 2018.
Assessments by Public Services and Procurement Canada show there were many issues with the building, such as decaying structure, failing building systems and hazardous materials on site.
At a press conference on Monday afternoon, Procurement Minister Helena Jaczek praised the auditor’s report for updating Canadians on the “historic progress” being made.
“Once restored, it will be a model for sustainability, and an inclusive and accessible space for all Canadians,” she said.
Jaczek said the Liberal government anticipates the project will create more than 70,000 jobs over the course of construction, with over 90 per cent of the work going toward small- and medium-sized businesses.
This report by The Canadian Press was first published March 27, 2023.