NEB approves Manitoba Hydro's proposed link to Minnesota

Hey there, time traveller!
This article was published 15/11/2018 (213 days ago), so information in it may no longer be current.

The National Energy Board has given the green light to Manitoba Hydro to build a transmission line to Minnesota -- subject to 28 conditions.

In a decision announced after the markets closed Thursday, the NEB released a 190-page report on the Manitoba-Minnesota Transmission Project.

Before the 213-kilometre, 500-kilovolt line -- that would run to near the village of Piney at the American border, where it would link up with the Great Northern Transmission line in the U.S., from the Dorsey converter station northwest of Winnipeg -- can go ahead, it needs federal government approval and the provincial government to issue a licence.

In a teleconference Thursday, two NEB officials gave the reasons for the quasi-judicial board's approval of the project.

Get the full story.
No credit card required. Cancel anytime.

Join free for 30 days

After that, pay as little as $0.99 per month for the best local news coverage in Manitoba.

 

Already a subscriber?

Log in

Keep reading free:

I agree to the Terms and Conditions, Cookie and Privacy Policies, and CASL agreement.

 

Already have an account?

Log in here »

Subscribers Log in below to continue reading,
not a subscriber? Create an account to start a 30 day free trial.

Log in Create your account

Your free trial has come to an end.

We hope you have enjoyed your trial! To continue reading, we recommend our Read Now Pay Later membership. Simply add a form of payment and pay only 27¢ per article.

For unlimited access to the best local, national, and international news and much more, try an All Access Digital subscription:

Thank you for supporting the journalism that our community needs!

Your free trial has come to an end.

We hope you have enjoyed your trial! To continue reading, we recommend our Read Now Pay Later membership. Simply add a form of payment and pay only 27¢ per article.

For unlimited access to the best local, national, and international news and much more, try an All Access Digital subscription:

Thank you for supporting the journalism that our community needs!

We hope you have enjoyed your free trial!

To continue reading, select a plan below:

All Access Digital

Introductory pricing*

99¢

per month

  • Unlimited online reading and commenting
  • Daily newspaper replica e-Edition
  • News Break - our award-winning iOS app
  • Exclusive perks & discounts
Continue

Read Now Pay Later

Pay

27¢

per article

  • Commitment-free
  • Cancel anytime
  • Only pay for what you read
  • Refunds available
Continue

*Introductory pricing schedule for 12 month: $0.99/month plus tax for first 3 months, $5.99/month for months 4 - 6, $10.99/month for months 7 - 9, $13.99/month for months 10 - 12. Standard All Access Digital rate of $16.99/month begins after first year.

We hope you have enjoyed your free trial!

To continue reading, select a plan below:

Read Now Pay Later

Pay

27¢

per article

  • Commitment-free
  • Cancel anytime
  • Only pay for what you read
  • Refunds available
Continue

All Access Digital

Introductory pricing*

99¢

per month

  • Unlimited online reading and commenting
  • Daily newspaper replica e-Edition
  • News Break - our award-winning iOS app
  • Exclusive perks & discounts
Continue

Mon to Sat Delivery

Pay

$34.36

per month

  • Includes all benefits of All Access Digital
  • 6-day delivery of our award-winning newspaper
Continue

*Introductory pricing schedule for 12 month: $0.99/month plus tax for first 3 months, $5.99/month for months 4 - 6, $10.99/month for months 7 - 9, $13.99/month for months 10 - 12. Standard All Access Digital rate of $16.99/month begins after first year.

We hope you have enjoyed your free trial!

To continue reading, select a plan below:

All Access Digital

Introductory pricing*

99¢

per month

  • Unlimited online reading and commenting
  • Daily newspaper replica e-Edition
  • News Break - our award-winning iOS app
  • Exclusive perks & discounts
Continue

Read Now Pay Later

Pay

27¢

per article

  • Commitment-free
  • Cancel anytime
  • Only pay for what you read
  • Refunds available
Continue

*Introductory pricing schedule for 12 month: $0.99/month plus tax for first 3 months, $5.99/month for months 4 - 6, $10.99/month for months 7 - 9, $13.99/month for months 10 - 12. Standard All Access Digital rate of $16.99/month begins after first year.

We hope you have enjoyed your free trial!

To continue reading, select a plan below:

Read Now Pay Later

Pay

27¢

per article

  • Commitment-free
  • Cancel anytime
  • Only pay for what you read
  • Refunds available
Continue

All Access Digital

Introductory pricing*

99¢

per month

  • Unlimited online reading and commenting
  • Daily newspaper replica e-Edition
  • News Break - our award-winning iOS app
  • Exclusive perks & discounts
Continue

*Introductory pricing schedule for 12 month: $0.99/month plus tax for first 3 months, $5.99/month for months 4 - 6, $10.99/month for months 7 - 9, $13.99/month for months 10 - 12. Standard All Access Digital rate of $16.99/month begins after first year.

Hey there, time traveller!
This article was published 15/11/2018 (213 days ago), so information in it may no longer be current.

The National Energy Board has given the green light to Manitoba Hydro to build a transmission line to Minnesota — subject to 28 conditions.

In a decision announced after the markets closed Thursday, the NEB released a 190-page report on the Manitoba-Minnesota Transmission Project.

Before the 213-kilometre, 500-kilovolt line — that would run to near the village of Piney at the American border, where it would link up with the Great Northern Transmission line in the U.S., from the Dorsey converter station northwest of Winnipeg — can go ahead, it needs federal government approval and the provincial government to issue a licence.

In a teleconference Thursday, two NEB officials gave the reasons for the quasi-judicial board's approval of the project.

They said after hearing arguments for and against the line, the board decided environmental and Indigenous concerns could be mitigated and there was an economic benefit to the province if it granted approval.

"The board was satisfied that the economic impact can be positive compared to the project not being built," NEB chief economist Jean-Denis Charlebois said.

The board's chief environment officer, Robert Steedman, said it is satisfied issues raised by Indigenous communities can be fairly addressed. At least 20 per cent of the project's "content" — including jobs and materials — has to be Indigenous.

Work on the line will be conducted when the ground is frozen to reduce the potential effects on the environment, outside of bird breeding and ungulate (hoofed animal) calving season, Steedman said.

Manitoba Hydro first pitched its project description for a transmission line to Minnesota to the NEB in October 2015. The transmission project seeks to give Hydro more leeway to market electricity to the U.S.

 

The Crown corporation hopes to have the line in service by 2020.

"We're pretty pleased with the NEB's decision," Hydro spokesman Scott Powell said Thursday. He couldn't say how long it might take before the line starts getting built, nor what meeting the 28 conditions will require.

"We're currently studying the document," Powell said.

Download NEB: Reasons for decision

The MMTP has been subject to multiple hearings from the Manitoba Clean Environment Commission and the NEB.

Manitobans, including First Nations that would be affected by construction of the line, voiced their concerns in both processes.

The Manitoba Metis Federation has said it made a deal with Hydro to be paid $67.5-million over 50 years, so as not to oppose the MMTP and as compensation for other past and future Hydro projects.

Hydro referred to the proposed deal as little more than a "term sheet." Premier Brian Pallister described the arrangement as "hush money," and spiked the idea.

The MMF is now fighting the matter in court. On Thursday, the NEB said it couldn't comment on the matter, as it is between the province and Métis federation.

— with files from Jessica Botelho-Urbanski

Carol Sanders

Carol Sanders
Reporter

Carol Sanders’ reporting on newcomers to Canada has made international headlines, earned national recognition but most importantly it’s shared the local stories of the growing diversity of people calling Manitoba home.

Read full biography

You can comment on most stories on The Winnipeg Free Press website. You can also agree or disagree with other comments. All you need to do is be a Winnipeg Free Press print or digital subscriber to join the conversation and give your feedback.

Have Your Say

Have Your Say

Comments are open to The Winnipeg Free Press print or digital subscribers only. why?

Have Your Say

Comments are open to The Winnipeg Free Press Subscribers only. why?

By submitting your comment, you agree to abide by our Community Standards and Moderation Policy. These guidelines were revised effective February 27, 2019. Have a question about our comment forum? Check our frequently asked questions.