Portage and Main overhaul could hit $47M

Engineering report says waterproofing membrane, most mechanical and electrical systems need replacing

Advertisement

Advertise with us

The City of Winnipeg was once warned the full cost to repair and update the underground concourse at Portage Avenue and Main Street could reach as high as $46.8 million.

Read this article for free:

or

Already have an account? Log in here »

To continue reading, please subscribe:

Monthly Digital Subscription

$1 per week for 24 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*Billed as $4.00 plus GST every four weeks. After 24 weeks, price increases to the regular rate of $19.00 plus GST every four weeks. Offer available to new and qualified returning subscribers only. Cancel any time.

Monthly Digital Subscription

$4.75/week*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles

*Billed as $19 plus GST every four weeks. Cancel any time.

To continue reading, please subscribe:

Add Winnipeg Free Press access to your Brandon Sun subscription for only

$1 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Start now

No thanks

*$1 will be added to your next bill. After your 4 weeks access is complete your rate will increase by $0.00 a X percent off the regular rate.

Hey there, time traveller!
This article was published 31/12/2020 (1738 days ago), so information in it may no longer be current.

The City of Winnipeg was once warned the full cost to repair and update the underground concourse at Portage Avenue and Main Street could reach as high as $46.8 million.

That potential tab includes $12.6 million to repair the underground over the next 10 years ($16.8 million with inflation), according to the “Portage & Main Underground Concourse Facility Condition Assessment report” written by SMS Engineering Ltd. in May 2019. The cost could soar another $15 million to $20 million higher, if surface work to get access to the roof membrane is included, raising the total price to $32.6 million ($46.8 million with inflation), the report adds.

The report cautions that the roof membrane price is a preliminary estimate.

JOHN WOODS / WINNIPEG FREE PRESS
The city of Winnipeg has sent out a request for proposals to renovate the underground concourse at Portage and Main.
JOHN WOODS / WINNIPEG FREE PRESS The city of Winnipeg has sent out a request for proposals to renovate the underground concourse at Portage and Main.

The city stresses there’s still work to do to pin down a final price.

“At this point in time, those estimates… do not include actual costs or contingencies,” said Kalen Qually, a city spokesperson, in an email.

The engineering report was posted online with a new request for proposals. The RFP seeks a consultant to design the most immediate and critical underground repairs at the Portage and Main concourse, which opened in 1979, and determine a more refined cost estimate for the work.

That plan will address repairs that are required over the next five to 10 years to keep the concourse “accessible and available to the public while the city continues to develop a more comprehensive investment strategy,” wrote Qually.

The head of council’s property and development committee said the need for repairs at the aging concourse is obvious.

“There’s a lot of work that we know needs to be done. Of course, any time we have (a price estimate) that high it is a bit of a shock… We would have to look at this closely,” said Coun. Cindy Gilroy (Daniel McIntyre).

Gilroy said she believes some of the repairs are critical, including those that address safety.

The engineering report details many problems at the aging concourse, including a Portage Avenue skylight that “leaks during any major rain event.”

It concludes the waterproofing membrane, most of the mechanical systems and most of the electrical systems are “beyond their theoretical service life” and should be replaced. It also found the site’s “obsolete” fire alarm doesn’t meet current code or life safety standards.

Investments in Portage and Main have become a hot topic, especially since Winnipeggers voted against reopening the intersection’s above-ground crossing to pedestrians in 2018.

Coun. Brian Mayes, a former property and development chairperson, stressed the underground repairs can’t be ignored, even if pedestrian access never resumes.

“It’s not like if we just agreed to crossing at grade, we could have avoided all this cost. It’s some aging infrastructure that needs to be fixed up,” said Mayes.

JOHN WOODS / WINNIPEG FREE PRESS
The underground concourse at Portage and Main in Winnipeg Wednesday.
JOHN WOODS / WINNIPEG FREE PRESS The underground concourse at Portage and Main in Winnipeg Wednesday.

The RFP calls for detailed drawings to repair leakage to concrete foundation walls, a complete roofing system replacement and a skylight replacement at 210 Portage Ave. It also calls for repair and/or replacement plans for some electrical, pipe, HVAC (heating, ventilation, and air conditioning system), and fire protection elements.

While the contractor is expected to provide a schedule for the work, the RFP notes “the city has no obligation to proceed with the construction services… until sufficient funding is available.”

Qually confirmed funding has not been approved for the construction work at this point. The city expects to award the contract in March 2021.

Coun. Jeff Browaty said the public service will also seek a second consultant in January to address “intersection revitalization” for Portage and Main, which he said would look at sidewalk enhancements and the renewal of the roof membrane.

However, Browaty stressed he believes the city must complete access agreements with property owners at the intersection before it sets aside new funding for the concourse.

“I don’t think we should be spending a single dime right now, until we figure out what the sharing agreement is going to be with our partners, beyond the absolute bare minimum in maintenance to keep it open,” he said.

Browaty, who was a vocal opponent of reopening Portage and Main to pedestrians, said he agrees some underground upgrades and repairs are necessary.

Joyanne.pursaga@freepress.mb.ca

Twitter: @joyanne_pursaga

Joyanne Pursaga

Joyanne Pursaga
Reporter

Joyanne is city hall reporter for the Winnipeg Free Press. A reporter since 2004, she began covering politics exclusively in 2012, writing on city hall and the Manitoba Legislature for the Winnipeg Sun before joining the Free Press in early 2020. Read more about Joyanne.

Every piece of reporting Joyanne produces is reviewed by an editing team before it is posted online or published in print — part of the Free Press‘s tradition, since 1872, of producing reliable independent journalism. Read more about Free Press’s history and mandate, and learn how our newsroom operates.

Our newsroom depends on a growing audience of readers to power our journalism. If you are not a paid reader, please consider becoming a subscriber.

Our newsroom depends on its audience of readers to power our journalism. Thank you for your support.

Report Error Submit a Tip

Local

LOAD MORE